2237 3/4 S COCHRAN AVE 90016

Certificate Information: 2237 3/4 S COCHRAN AVE 90016

Application / Permit
24014-10000-00033
Plan Check / Job No.
B23LA24630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION ( 15' X 12' ) AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 4/30/2024
Issuing Office
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2024 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 ALEC MOUSAKHANIAN
Corrections Issued 1/19/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 4/5/2024 ROSENDO MEDINA
Plan Check Approved 4/11/2024 ROSENDO MEDINA
Issued 4/30/2024 APPLICANT
CofO in Progress 7/16/2025 ARTHUR NEGRETE
No Progress 8/24/2025 DEROLD HAUFF
CofO in Progress 8/24/2025 DEROLD HAUFF
Permit Finaled 9/5/2025 DEROLD HAUFF
CofO Issued 9/5/2025 DEROLD HAUFF
Permit Finaled 9/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/6/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/14/2024 DAVID LOPEZ
Sewer availability Cleared 3/14/2024 DAVID LOPEZ
Address approval Cleared 3/26/2024 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/5/2024 Approved JOSE MACIAS
Pre-Inspection 1/10/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 1/21/2025 Partial Approval ARTHUR NEGRETE
Footing/Foundation/Slab 1/27/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 1/27/2025 Approved ARTHUR NEGRETE
Sewer 3/6/2025 Partial Approval ARTHUR NEGRETE
Special/Order Compliance 3/6/2025 Partial Inspection ALEX COLIN
Special/Order Compliance 3/10/2025 Partial Inspection ALEX COLIN
Wood Frame 3/10/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 4/9/2025 Approved RONNIE MINDANAO
PLUMBING-Rough 4/9/2025 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 4/16/2025 Approved ARTHUR NEGRETE
Insulation 4/22/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/22/2025 Approved ARTHUR NEGRETE
Drywall Nailing 5/28/2025 Approved ARTHUR NEGRETE
Green Building Rough 5/28/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/3/2025 Approved ARTHUR NEGRETE
HVAC-Rough 6/3/2025 Approved ARTHUR NEGRETE
Sewer 6/3/2025 Approved ARTHUR NEGRETE
Underground Mechanical 6/3/2025 Approved ARTHUR NEGRETE
Shower Pan 6/9/2025 Approved ARTHUR NEGRETE
Service/Power Release 6/27/2025 Not Ready for Inspection ARTHUR NEGRETE
Final 7/2/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 7/2/2025 Conditional Approval ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/2/2025 Approved ARTHUR NEGRETE
Final 7/15/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 7/15/2025 Approved ARTHUR NEGRETE
Service/Power Release 7/15/2025 Approved ARTHUR NEGRETE