2112 S PELHAM AVE 90025
Certificate Information: 2112 S PELHAM AVE 90025
- Application / Permit
- 24014-10000-00024
- Plan Check / Job No.
- B24LA00071
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: convert exisitng detached garage (188sqft) + addtion (77sqft) to ADU (265sqft) with storage addtion (72sqft) and attached trellis (21sqft) per engineer details CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2024 | AUNG SOE |
| Corrections Issued | 1/16/2024 | AUNG SOE |
| Applicant returned to address corrections | 2/8/2024 | KHUONG TRUONG |
| Plan Check Approved | 6/13/2024 | KHUONG TRUONG |
| Issued | 6/13/2024 | APPLICANT |
| CofO in Progress | 5/7/2025 | DANIEL VERA |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
| CofO Issued | 5/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/17/2024 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 1/22/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 2/20/2024 | FREDDY GARCIA |
| Roof/Waste drainage to street | Cleared | 2/22/2024 | VLADIMIR ARUTYUNYAN |
| Construction near power lines | Cleared | 5/30/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/30/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Kor Design Build; Lic. No.: 1026877-B | , |
| Engineer | David, Lee Reith; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/28/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 10/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/4/2024 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/9/2024 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 10/22/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/1/2024 | Corrections Issued | MICHAEL PELHAM |
| Insulation | 11/5/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/5/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 11/14/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/20/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 1/17/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/29/2025 | Approved | STEPHANIE SWANSON |
| Final | 2/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 2/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/29/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 4/29/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 4/29/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 4/29/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 4/30/2025 | Approved | DANIEL VERA |
| Final | 5/6/2025 | OK to Issue CofO | DANIEL VERA |