2022 S MIDVALE AVE 90025
Certificate Information: 2022 S MIDVALE AVE 90025
- Application / Permit
- 24014-10000-00013
- Plan Check / Job No.
- B23LA24604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. NFPA 13D FIRE SPRINKLERS REQUIRED. 1st FLOOR AND 2nd FLOOR ADDITION TO (E) 1-STORY SFD WITH NEW ATTACHED 2-CAR GARAGE AND NEW ATTACHED OPEN DECK.
- Permit Issued
- Issued on 3/21/2024
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/18/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/25/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/28/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/21/2024 | KEVIN MORALES |
| Issued | 3/21/2024 | APPLICANT |
| CofO in Progress | 11/25/2024 | BOBBY KEY |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 2/1/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 2/13/2024 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 2/14/2024 | VASIL MIHALEV |
| Low Impact Development (LID) | Cleared | 2/26/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/28/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/29/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 2/29/2024 | ANDREA SAINT-ANTONIN |
| GPI Written Notices | Cleared | 3/21/2024 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/19/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/22/2024 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 5/3/2024 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 5/3/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/24/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 5/24/2024 | Not Ready for Inspection | KIRK SANDERS |
| Sewer | 6/4/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/4/2024 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 6/20/2024 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 6/28/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 7/3/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 7/3/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 7/9/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 7/11/2024 | Approved | KIRK SANDERS |
| Shower Pan | 7/11/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/15/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Rough | 7/15/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | KIRK SANDERS |
| METHANE-Rough | 7/17/2024 | Approved | KIRK SANDERS |
| Wood Frame | 7/17/2024 | Approved | KIRK SANDERS |
| Insulation | 7/19/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 7/30/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/5/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/7/2024 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 10/7/2024 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 10/10/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 10/10/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 10/17/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 10/17/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 10/17/2024 | Approved | KIRK SANDERS |
| Final | 10/22/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 10/22/2024 | Approved | KIRK SANDERS |
| Final | 11/25/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 11/25/2024 | Approved | BOBBY KEY |
| Service/Power Release | 11/25/2024 | Approved | BOBBY KEY |