3915 N BERRY DR 91604

Certificate Information: 3915 N BERRY DR 91604

Application / Permit
24014-10000-00005
Plan Check / Job No.
B23LA24588
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. 2nd story addition over existing (E) garage for (E) SFD.
Permit Issued
Issued on 2/26/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/5/2024 JASON JANGADA
Corrections Issued 1/5/2024 JASON JANGADA
Applicant returned to address corrections 2/7/2024 JASON JANGADA
Plan Check Approved 2/22/2024 JASON JANGADA
Issued 2/26/2024 APPLICANT
CofO in Progress 3/16/2025 CHRISTOPHE COCHRAN
Permit Finaled 5/2/2025 RUBEN SALAS
CofO Issued 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/25/2024 COLIN LOREDO
Sewer availability Cleared 1/25/2024 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/26/2024 COLIN LOREDO
Grading Pre-Inspection Cleared 2/7/2024 JASON JANGADA

Contact Information

Contractor Owner-Builder       ,
Engineer Arutyunyan,, Vladimir; Lic. No.: C92714 3235 KIRKHAM DR      GLENDALE, CA 91206

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2024 Corrections Issued CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 3/12/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/12/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/12/2024 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/19/2024 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/17/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 4/17/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 4/17/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 6/11/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/12/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 6/12/2024 Approved CHRISTOPHE COCHRAN
Insulation 6/18/2024 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/18/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 6/21/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved KEVIN BERBERYAN
Insulation 6/21/2024 Approved KEVIN BERBERYAN
Wood Frame 6/21/2024 Approved KEVIN BERBERYAN
Drywall Nailing 6/27/2024 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 6/27/2024 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 7/10/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/12/2024 Approved RYAN SALAZAR
Deputy Wood Construction 7/15/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 12/10/2024 Approved CHRISTOPHE COCHRAN
Final 12/10/2024 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/10/2024 Approved CHRISTOPHE COCHRAN
Green Building Final 12/10/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 12/10/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/10/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 3/13/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 3/13/2025 Approved CHRISTOPHE COCHRAN
Smoke Detectors 3/13/2025 Approved CHRISTOPHE COCHRAN