12742 W HIGHWOOD ST 90049
Certificate Information: 12742 W HIGHWOOD ST 90049
- Application / Permit
- 24014-10000-00004
- Plan Check / Job No.
- B24LA00017
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | DANIEL YIP |
| Corrections Issued | 1/9/2024 | DANIEL YIP |
| Quality Review Completed | 1/10/2024 | KEN GILL |
| Building Plans Picked Up | 1/17/2024 | APPLICANT |
| Plan Check Approved | 2/14/2024 | DANIEL YIP |
| No Progress | 2/14/2024 | DANIEL YIP |
| Plan Check Approved | 2/15/2024 | DANIEL YIP |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 1/24/2025 | EVAN COOPER |
| CofO Issued | 2/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/2/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 2/7/2024 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2024 | BRENDEN HAWK |
Contact Information
| Contractor | S Visions Construction Ii Inc; Lic. No.: 999353-B | 4413 COLDWATER CANYON AVE STUDIO CITY, CA 91604 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/11/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 4/12/2024 | Approved | VASIL MIHALEV |
| Wood Frame | 5/2/2024 | Partial Inspection | KEVIN SARGSYAN |
| Wood Frame | 6/10/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Partial Approval | EVAN COOPER |
| Wood Frame | 6/25/2024 | Corrections Issued | EVAN COOPER |
| Deputy Wood Construction | 7/15/2024 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/15/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/15/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/15/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 7/17/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/19/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/29/2024 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 7/29/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 7/30/2024 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | EVAN COOPER |
| Insulation | 8/2/2024 | Approved | EVAN COOPER |
| Shower Pan | 8/2/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 8/6/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/6/2024 | Approved | TEMISTOCLES CAAL |
| Final | 1/3/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/3/2025 | Approved | KEVIN SARGSYAN |
| Green Building Final | 1/3/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 1/3/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/24/2025 | Approved | EVAN COOPER |
| Final | 1/24/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 1/24/2025 | Approved | EVAN COOPER |
| MERV13>=Final | 1/24/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/24/2025 | Approved | EVAN COOPER |