12742 W HIGHWOOD ST 90049

Certificate Information: 12742 W HIGHWOOD ST 90049

Application / Permit
24014-10000-00004
Plan Check / Job No.
B24LA00017
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 2/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 DANIEL YIP
Corrections Issued 1/9/2024 DANIEL YIP
Quality Review Completed 1/10/2024 KEN GILL
Building Plans Picked Up 1/17/2024 APPLICANT
Plan Check Approved 2/14/2024 DANIEL YIP
No Progress 2/14/2024 DANIEL YIP
Plan Check Approved 2/15/2024 DANIEL YIP
Issued 2/22/2024 APPLICANT
CofO in Progress 1/24/2025 EVAN COOPER
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/2/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 2/7/2024 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 2/15/2024 BRENDEN HAWK

Contact Information

Contractor S Visions Construction Ii Inc; Lic. No.: 999353-B 4413 COLDWATER CANYON AVE      STUDIO CITY, CA 91604
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 4/11/2024 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 4/12/2024 Approved VASIL MIHALEV
Wood Frame 5/2/2024 Partial Inspection KEVIN SARGSYAN
Wood Frame 6/10/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Partial Approval EVAN COOPER
Wood Frame 6/25/2024 Corrections Issued EVAN COOPER
Deputy Wood Construction 7/15/2024 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/15/2024 Approved ARAM AVEDISIAN
HVAC-Rough 7/15/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/15/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 7/17/2024 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/19/2024 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 7/29/2024 Corrections Issued EVAN COOPER
Green Building Rough 7/29/2024 Approved EVAN COOPER
Interior/Exterior Lathing 7/29/2024 Partial Approval EVAN COOPER
Deputy Wood Construction 7/30/2024 Conditional Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 8/2/2024 Approved EVAN COOPER
Insulation 8/2/2024 Approved EVAN COOPER
Shower Pan 8/2/2024 Approved EVAN COOPER
Drywall Nailing 8/6/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 8/6/2024 Approved TEMISTOCLES CAAL
Final 1/3/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/3/2025 Approved KEVIN SARGSYAN
Green Building Final 1/3/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/3/2025 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 1/3/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/24/2025 Approved EVAN COOPER
Final 1/24/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 1/24/2025 Approved EVAN COOPER
MERV13>=Final 1/24/2025 Approved EVAN COOPER
PLUMBING-Final 1/24/2025 Approved EVAN COOPER