528 W 43RD ST 90037
Certificate Information: 528 W 43RD ST 90037
- Application / Permit
- 24010-70000-04197
- Plan Check / Job No.
- B24SL00730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2024 | FERNANDO FLORES |
| Corrections Issued | 10/8/2024 | FERNANDO FLORES |
| Building Plans Picked Up | 10/9/2024 | APPLICANT |
| Plan Check Approved | 10/22/2024 | FERNANDO FLORES |
| Issued | 10/22/2024 | APPLICANT |
| CofO in Progress | 4/7/2025 | SABAS ALONSO |
| Permit Finaled | 4/10/2025 | DEROLD HAUFF |
| CofO Issued | 4/10/2025 | DEROLD HAUFF |
| Permit Finaled | 4/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/17/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 10/29/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/1/2024 | Approved | JOAQUIN GREENOUGH |
| Special/Order Compliance | 11/1/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/25/2024 | No Access for Inspection | SABAS ALONSO |
| HVAC-Rough | 11/25/2024 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 11/25/2024 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/27/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/3/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/3/2024 | Approved | SABAS ALONSO |
| Insulation | 12/12/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/12/2024 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 12/16/2024 | No Access for Inspection | SABAS ALONSO |
| HVAC-Rough | 12/16/2024 | No Access for Inspection | SABAS ALONSO |
| Insulation | 12/16/2024 | No Access for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 12/16/2024 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 12/16/2024 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | SABAS ALONSO |
| Green Building Final | 12/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 12/18/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/18/2024 | Approved | SABAS ALONSO |
| Insulation | 12/18/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/18/2024 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 12/23/2024 | Approved | ANTHONY RAMOS |
| Final | 3/24/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/24/2025 | Approved | SABAS ALONSO |
| MERV13>=Final | 3/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 3/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 3/24/2025 | Approved | SABAS ALONSO |
| Final | 3/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| MERV13>=Final | 3/27/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 3/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/3/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 4/3/2025 | Approved | SABAS ALONSO |