2120-2120 1/2 E 92ND ST 90002
Certificate Information: 2120-2120 1/2 E 92ND ST 90002
- Application / Permit
- 24010-70000-03937
- Plan Check / Job No.
- B24SL00679
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACEHD ADU (2-UNIT) PER CA 65852.2(e)(1)(D) AND APPLICABLE PART OF LAMC 12.22A.33(c)-(d), (g). WITH ATTACHED 2-CAR GARAGE NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO. COMPLY WITH DEPARTMENT ORDER effective date 10/21/2014. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 5/9/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 5/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | VIVIAN LAO |
| Corrections Issued | 9/24/2024 | VIVIAN LAO |
| Quality Review Completed | 9/27/2024 | KEN GILL |
| Applicant returned to address corrections | 4/14/2025 | VIVIAN LAO |
| Plan Check Approved | 4/22/2025 | VIVIAN LAO |
| Issued | 5/9/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | ARTHUR NEGRETE |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 12/10/2024 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/6/2025 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/18/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 7/18/2025 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/4/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/8/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 1/8/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/12/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 1/12/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 1/16/2026 | Corrections Issued | ARTHUR NEGRETE |
| Insulation | 1/21/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 2/24/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/8/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 5/8/2026 | Approved | ARTHUR NEGRETE |
| Final | 5/11/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 5/11/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/11/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 5/11/2026 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 5/11/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 5/27/2026 | Approved | ARTHUR NEGRETE |