629 3/4 E 80TH ST 90001
Certificate Information: 629 3/4 E 80TH ST 90001
- Application / Permit
- 24010-70000-02601
- Plan Check / Job No.
- B24SL00136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Metro
- Current Status
- Issued on 6/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | JAD BASMA |
| Corrections Issued | 7/15/2024 | JAD BASMA |
| Quality Review Completed | 7/19/2024 | KEN GILL |
| Building Plans Picked Up | 7/30/2024 | APPLICANT |
| Applicant returned to address corrections | 5/15/2025 | JAD BASMA |
| Plan Check Approved | 6/4/2025 | JAD BASMA |
| Issued | 6/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/2/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 10/21/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 4/29/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/22/2025 | Partial Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 7/22/2025 | Approved | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | JOHN QUINTANILLA |
| Deputy Wood Construction | 11/3/2025 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/21/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 11/21/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 11/21/2025 | Corrections Issued | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 12/1/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 12/1/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/18/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 12/18/2025 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 12/22/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Rough | 12/22/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 12/22/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 2/9/2026 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/19/2026 | Approved | ALEX COLIN |
| Sewer | 4/22/2026 | Approved | JOHN QUINTANILLA |
| Shower Pan | 4/22/2026 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 4/22/2026 | Not Ready for Inspection | JOHN QUINTANILLA |