698 1/2 W 80TH ST 90044

Certificate Information: 698 1/2 W 80TH ST 90044

Application / Permit
24010-70000-02489
Plan Check / Job No.
B24SL00124
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story detached ADU PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). Building to be sprinklered throughout with NFPA 13R.
Permit Issued
Issued on 7/8/2025
Issuing Office
South Los Angeles
Current Status
Issued on 7/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/4/2024 RICARDO RAMIREZ
Corrections Issued 7/5/2024 RICARDO RAMIREZ
Quality Review Completed 7/25/2024 KEN GILL
Plan Check Approved 4/3/2025 RICARDO RAMIREZ
Issued 7/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/20/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/21/2024 TREVOR QUAN
Sewer availability Cleared 8/21/2024 TREVOR QUAN
"Q" conditions Cleared 8/27/2024 DAVID URITA
Construction near power lines Cleared 9/25/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 2/6/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/19/2025 RYAN CASTRO
Hydrant and Access approval Cleared 2/25/2025 RUEL COLE

Contact Information

Contractor Maison Construction Inc; Lic. No.: 1072238-B 6340 COLDWATER CANYON AVE #205      NORTH HOLLYWOOD, CA 91606
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/9/2025 Partial Approval JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/14/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/15/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 10/2/2025 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Verify Sprinkler Sign Off 10/7/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 10/23/2025 Corrections Issued JOHN QUINTANILLA
Interior/Exterior Lathing 10/23/2025 Approved JOHN QUINTANILLA
HVAC-Rough 10/24/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 10/24/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 11/4/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/12/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 11/12/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 11/12/2025 Partial Inspection JOHN QUINTANILLA
Wood Frame 11/12/2025 Partial Inspection JOHN QUINTANILLA
Shower Pan 11/14/2025 Approved JOHN QUINTANILLA
Wood Frame 11/14/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 11/25/2025 Approved ANTHONY RAMOS
Insulation 11/25/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 12/11/2025 Approved ANTHONY RAMOS
Insulation 12/11/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 12/11/2025 Approved ANTHONY RAMOS
Underground Mechanical 4/23/2026 Partial Inspection JOHN QUINTANILLA
Sewer 4/27/2026 Approved SABAS ALONSO
Underground Mechanical 4/27/2026 Approved SABAS ALONSO