930 N MCFARLAND AVE 90744
Certificate Information: 930 N MCFARLAND AVE 90744
- Application / Permit
- 24010-40000-03755
- Plan Check / Job No.
- B24SP03177
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY 30' X 32' A.D.U. PER ORDINANCE. CONST. PER W.F.P.P.
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/14/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/19/2024 | APPLICANT |
| Applicant returned to address corrections | 4/8/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 5/13/2025 | LAWRENCE QUIRANTE |
| Issued | 5/13/2025 | APPLICANT |
| CofO in Progress | 10/28/2025 | JOSEPH MCGARRY |
| Permit Finaled | 10/29/2025 | ANSON MAGLASANG |
| CofO Issued | 10/29/2025 | ANSON MAGLASANG |
| Permit Finaled | 10/29/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/24/2024 | XOCHITL ARQUIETA |
| Address approval | Cleared | 10/28/2024 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 10/30/2024 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/12/2025 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 6/12/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 6/12/2025 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 6/12/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | EUGENE CASSIDY |
| Insulation | 6/23/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/9/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/9/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/9/2025 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/9/2025 | Approved | EUGENE CASSIDY |
| Shower Pan | 7/9/2025 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/9/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/9/2025 | Approved | EUGENE CASSIDY |
| Insulation | 7/11/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/14/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/22/2025 | Approved | EUGENE CASSIDY |
| Sewer | 8/28/2025 | Approved | EUGENE CASSIDY |
| Final | 9/22/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/22/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/22/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 9/22/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/27/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Not Required | JOSEPH MCGARRY |
| Service/Power Release | 10/27/2025 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 10/27/2025 | Approved | JOSEPH MCGARRY |