1729 N LAGOON AVE 90744

Certificate Information: 1729 N LAGOON AVE 90744

Application / Permit
24010-40000-03348
Plan Check / Job No.
B24SP02877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY 30' X 41' IRREG.-SHAPED A.D.U. AT REAR OF LOT PER ORDINANCE. CONST. PER W.F.P.P.
Permit Issued
Issued on 4/8/2025
Issuing Office
San Pedro
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 LAWRENCE QUIRANTE
Corrections Issued 8/12/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 8/15/2024 APPLICANT
Applicant returned to address corrections 3/11/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/18/2025 LAWRENCE QUIRANTE
Plan Check Approved 3/25/2025 LAWRENCE QUIRANTE
Issued 4/8/2025 APPLICANT
CofO in Progress 3/13/2026 EUGENE CASSIDY
Permit Finaled 3/16/2026 ANSON MAGLASANG
CofO Issued 3/16/2026 ANSON MAGLASANG
Permit Finaled 3/16/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/8/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 9/8/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 9/12/2024 JILVER MAZARIEGOS
Sewer availability Cleared 9/12/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/10/2025 Partial Approval EUGENE CASSIDY
METHANE-Subgrade 9/10/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 9/10/2025 Approved EUGENE CASSIDY
Sewer 9/10/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/16/2025 Approved EUGENE CASSIDY
METHANE-Barrier 9/16/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/19/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/19/2025 Approved JOSEPH MCGARRY
HVAC-Rough 11/19/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 11/19/2025 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 11/24/2025 Approved EUGENE CASSIDY
Green Building Rough 11/24/2025 Approved EUGENE CASSIDY
Insulation 11/24/2025 Approved EUGENE CASSIDY
METHANE-Rough 11/24/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 11/24/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/26/2025 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/2/2025 Partial Approval EUGENE CASSIDY
Shower Pan 12/2/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 12/22/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 12/22/2025 Approved EUGENE CASSIDY
Underground Mechanical 12/22/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/24/2026 Corrections Issued JOSEPH MCGARRY
Final 2/24/2026 Corrections Issued JOSEPH MCGARRY
Gas Test 2/24/2026 Approved JOSEPH MCGARRY
Green Building Final 2/24/2026 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 2/24/2026 Approved JOSEPH MCGARRY
ELECTRICAL-Final 3/13/2026 Approved EUGENE CASSIDY
Final 3/13/2026 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/13/2026 Approved EUGENE CASSIDY
PLUMBING-Final 3/13/2026 Approved EUGENE CASSIDY
Service/Power Release 3/13/2026 Approved EUGENE CASSIDY