317-319 W F ST 90744
Certificate Information: 317-319 W F ST 90744
- Application / Permit
- 24010-40000-02049
- Plan Check / Job No.
- B24SP00096
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 2-STORY 26' x 45' DUPLEX BEHIND FRONT UNIT.
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/31/2024 | LAWRENCE QUIRANTE |
| Quality Review Completed | 6/5/2024 | JOHN FRANCIA |
| Building Plans Picked Up | 6/6/2024 | APPLICANT |
| Plan Check Approved | 6/13/2024 | LAWRENCE QUIRANTE |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 2/19/2025 | EUGENE CASSIDY |
| CofO Issued | 2/19/2025 | ANSON MAGLASANG |
| Permit Finaled | 2/19/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/7/2024 | YINGSHI HUANG |
| Address approval | Cleared | 6/10/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2024 | KHAING AYE |
| Sewer availability | Cleared | 6/12/2024 | KHAING AYE |
Contact Information
| Contractor | Hilltop Design-Build Inc; Lic. No.: 969696-B | 1441 W 7TH STREET 2ND FLOOR SAN PEDRO, CA 90732 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Partial Approval | EUGENE CASSIDY |
| METHANE-Subgrade | 7/2/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/10/2024 | Approved | JAMES CHAVEZ |
| METHANE-Barrier | 7/10/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 9/17/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 9/17/2024 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 9/17/2024 | Corrections Issued | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 9/17/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/24/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 10/24/2024 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 10/30/2024 | Approved | EUGENE CASSIDY |
| Insulation | 10/30/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 11/7/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/7/2024 | Approved | ANTHONY EGSON |
| Final | 2/4/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/4/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Not Required | EUGENE CASSIDY |
| Smoke Detectors | 2/4/2025 | Approved | EUGENE CASSIDY |
| Wood Frame | 2/4/2025 | Approved | EUGENE CASSIDY |
| Final | 2/13/2025 | OK to Issue CofO | EUGENE CASSIDY |