1080 1/2 S WEST BLVD 90019
Certificate Information: 1080 1/2 S WEST BLVD 90019
- Application / Permit
- 24010-40000-00948
- Plan Check / Job No.
- B24SP00041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW 1-STORY 22' X 30' ACCESSORY DWELLING UNIT PER gcs 65852.2(e)(1)(D) STATE LAW.
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/14/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/16/2024 | APPLICANT |
| Plan Check Approved | 12/19/2024 | TSE MING HUANG |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 11/12/2025 | JUSTIN HAWLEY |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
| CofO Issued | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 5/30/2024 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 9/13/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 10/31/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/12/2024 | XOCHITL ARQUIETA |
Contact Information
| Architect | Riblett,, Robert Warren; Lic. No.: C25170 | 1707 VIA EL PRADO #202 REDONDO BEACH, CA 90277 |
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/23/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 12/26/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/26/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 12/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/13/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/13/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/13/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 1/14/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 1/15/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 1/15/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/15/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/23/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 1/23/2025 | Conditional Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 1/27/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 1/27/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/27/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 1/27/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 1/28/2025 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 1/28/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 1/30/2025 | Approved | JUSTIN HAWLEY |
| Sewer | 2/18/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/3/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/3/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Final | 4/3/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 4/3/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/4/2025 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 4/5/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/5/2025 | Off-Hour Fees Due | |
| Final | 6/13/2025 | Corrections Issued | JUSTIN HAWLEY |
| Pre-Inspection | 7/8/2025 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 7/8/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/29/2025 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 9/29/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 9/29/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 11/12/2025 | Approved | JUSTIN HAWLEY |
| Final | 11/12/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 11/12/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 11/12/2025 | Approved | JUSTIN HAWLEY |