333 1/2 E STOWE TER 90042
Certificate Information: 333 1/2 E STOWE TER 90042
- Application / Permit
- 24010-30000-05004
- Plan Check / Job No.
- B24WL09482
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER LAMC 12.22A33(c) & (d) IN THE REAR OF THE LOT.
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/13/2024 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 12/27/2024 | APPLICANT |
| Applicant returned to address corrections | 4/9/2025 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 4/17/2025 | JAHANSHAH POURHASSAN |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 12/23/2025 | LILIANA PORTILLO |
| Permit Finaled | 12/23/2025 | DEROLD HAUFF |
| CofO Issued | 12/23/2025 | DEROLD HAUFF |
| Permit Finaled | 12/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/26/2024 | PATRICK PEREZ |
| Address approval | Cleared | 1/3/2025 | ABEL CASILLAS |
| BHO/Hillside ordinance | Cleared | 1/3/2025 | ABEL CASILLAS |
| BHO/Hillside ordinance | Cleared | 1/3/2025 | ABEL CASILLAS |
| BHO/Hillside ordinance | Cleared | 1/3/2025 | ABEL CASILLAS |
| BHO/Hillside ordinance | Cleared | 1/3/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 1/3/2025 | ABEL CASILLAS |
| CPC | Cleared | 1/7/2025 | NATHALY DE LA PAZ |
| HPOZ | Cleared | 1/7/2025 | NATHALY DE LA PAZ |
| BHO/Hillside ordinance | Cleared | 1/13/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/13/2025 | ABEL CASILLAS |
| Miscellaneous | Cleared | 4/2/2025 | ALBERT TAM |
| Grading Pre-Inspection | Cleared | 4/9/2025 | JAHANSHAH POURHASSAN |
| Miscellaneous | Cleared | 4/9/2025 | JAHANSHAH POURHASSAN |
| GPI Written Notices | Cleared | 4/17/2025 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lombera,, Raymundo Alcaraz; Lic. No.: L7740 | 135 S JACKSON STREET #202 GLENDALE, CA 91205 |
| Engineer | Yu,, Irene; Lic. No.: C68382 | 3411 CAROLINE AVE CULVER CITY, CA 90232 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2025 | Partial Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/25/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 6/27/2025 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/7/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/7/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 8/6/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/6/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/8/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/15/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/15/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/19/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/19/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/19/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/19/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/19/2025 | Approved | LILIANA PORTILLO |
| Insulation | 8/20/2025 | Not Ready for Inspection | REGINA MENDEZ |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/3/2025 | Approved | LILIANA PORTILLO |
| Insulation | 9/3/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/3/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/8/2025 | Approved | GEM DE OCAMPO |
| ELECTRICAL-Final | 10/17/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 10/17/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 10/17/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 10/22/2025 | Approved | DAVID WILLIAMS |
| Final | 10/30/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/30/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/30/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV No Gas | LILIANA PORTILLO |
| Smoke Detectors | 10/30/2025 | Approved | LILIANA PORTILLO |
| Final | 12/22/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 12/22/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 12/22/2025 | Approved | LILIANA PORTILLO |