12250 W CALIFA ST 91607

Certificate Information: 12250 W CALIFA ST 91607

Application / Permit
24010-30000-04892
Plan Check / Job No.
B24WL09283
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2 STORY DETACHED ADU PER LAMC 12.22 A.33 (c)--(d)
Permit Issued
Issued on 6/26/2025
Issuing Office
Valley
Current Status
Issued on 6/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 BEHROUZ KHOKHAR
Corrections Issued 12/6/2024 BEHROUZ KHOKHAR
Quality Review Completed 12/16/2024 CHIHARU SUZUKI
Building Plans Picked Up 12/16/2024 APPLICANT
Applicant returned to address corrections 1/31/2025 BEHROUZ KHOKHAR
Applicant returned to address corrections 2/19/2025 BEHROUZ KHOKHAR
Plan Check Approved 2/28/2025 BEHROUZ KHOKHAR
Issued 6/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/23/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 12/23/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 2/25/2025 KEVIN CHUNG
Sewer availability Cleared 2/25/2025 KEVIN CHUNG

Contact Information

Contractor Zone 26 Construction Inc; Lic. No.: 982096-B 18344 OXNARD STREET #106      TARZANA, CA 91356
Engineer Chen,, Junfei; Lic. No.: C85841 50 OUTLAW      IRVINE, CA 92602
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/27/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 8/8/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 8/8/2025 Approved GAREN HAYRAPETYAN
Pre-Inspection 8/26/2025 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 9/3/2025 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 9/24/2025 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/25/2025 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/5/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 12/5/2025 Not Ready for Inspection WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Approved WAYNE REGESTER
Green Building Rough 12/5/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Rough 12/5/2025 Approved WAYNE REGESTER
PLUMBING-Rough 12/5/2025 Approved WAYNE REGESTER
Verify Sprinkler Sign Off 12/5/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 12/19/2025 Approved WAYNE REGESTER
Green Building Rough 12/19/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 12/19/2025 Approved WAYNE REGESTER
Rough-Elec/Plmb/HVAC 12/19/2025 Approved WAYNE REGESTER
Insulation 12/26/2025 Partial Approval CHRISTOPHER MORFIN
Insulation 1/5/2026 Approved WAYNE REGESTER
Interior/Exterior Lathing 1/5/2026 Approved WAYNE REGESTER
Drywall Nailing 1/8/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 4/14/2026 Approved WAYNE REGESTER
Final 4/14/2026 Corrections Issued WAYNE REGESTER
Green Building Final 4/14/2026 Approved WAYNE REGESTER
HVAC-Final 4/14/2026 Approved WAYNE REGESTER
PLUMBING-Final 4/14/2026 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Approved WAYNE REGESTER
Service/Power Release 4/14/2026 Approved WAYNE REGESTER
Smoke Detectors 4/14/2026 Approved WAYNE REGESTER