11302 W COLLINS ST 1-2 91601

Certificate Information: 11302 W COLLINS ST 1-2 91601

Application / Permit
24010-30000-04859
Plan Check / Job No.
B24WL09205
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-Story Duplex with Attached Garage. Fully Sprinkled NFPA 13-D *** 1 of 3 ***
Permit Issued
Issued on 4/8/2025
Issuing Office
West Los Angeles
Current Status
Issued on 4/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 EDWIN ESPIN
Plans on Hold 11/26/2024 CHIHARU SUZUKI
Hold Released 12/4/2024 CHIHARU SUZUKI
Re-Activate Applicaton 12/4/2024 CHIHARU SUZUKI
Corrections Issued 12/18/2024 EDWIN ESPIN
Quality Review Completed 1/8/2025 KAVIAN REFAHI
Building Plans Picked Up 1/13/2025 APPLICANT
Applicant returned to address corrections 2/27/2025 EDWIN ESPIN
Plan Check Approved 3/21/2025 EDWIN ESPIN
Issued 4/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/19/2024 BIAINA HARITUNIAN
Highway dedication Cleared 12/19/2024 BIAINA HARITUNIAN
SB8 RUD Cleared 12/19/2024 ALYSSA FLORES
Sewer availability Cleared 12/19/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 1/2/2025 ERNEST TSE
Hydrant and Access approval Cleared 1/6/2025 KURT CORRAL
Roof/Waste drainage to street Cleared 1/15/2025 BIAINA HARITUNIAN
Frnt yard landscape/Water mgmt Cleared 2/14/2025 JASON CHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect May,, Philip S; Lic. No.: LA3104 60 VINTAGE      RANCHO MIRAGE, CA 92270

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 5/27/2025 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 6/13/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval JOSE AVILA
Deputy Wood Construction 7/16/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 7/30/2025 Conditional Approval JOSE AVILA
Deputy Wood Construction 7/30/2025 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Approved JOSE AVILA
HVAC-Rough 8/28/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/29/2025 Not Ready for Inspection JOSE AVILA
HVAC-Rough 9/26/2025 Approved JOSE AVILA
ELECTRICAL-Rough 10/7/2025 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 10/7/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/14/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 10/21/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Partial Approval JOSE AVILA
HVAC-Rough 10/21/2025 Approved JOSE AVILA
PLUMBING-Rough 10/21/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/6/2025 Approved JOSE AVILA
Shower Pan 11/6/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 11/17/2025 Corrections Issued JOSE AVILA
Green Building Rough 11/17/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/17/2025 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 11/17/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 11/18/2025 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 12/8/2025 Approved JOSE AVILA
Insulation 12/8/2025 Approved JOSE AVILA
Drywall Nailing 12/17/2025 Not Ready for Inspection MICHAEL CORTEZ
Wood Frame 12/19/2025 No Access for Inspection JOAQUIN GREENOUGH
Drywall Nailing 12/23/2025 Partial Approval JOSE AVILA
PLUMBING-Final 6/1/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/8/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 7/8/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/8/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/8/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/8/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/8/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 7/20/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 7/20/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/20/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/20/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/20/2026 Approved ROBERTO PALACIOS-LOPEZ