11302 W COLLINS ST 1-2 91601
Certificate Information: 11302 W COLLINS ST 1-2 91601
- Application / Permit
- 24010-30000-04859
- Plan Check / Job No.
- B24WL09205
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-Story Duplex with Attached Garage. Fully Sprinkled NFPA 13-D *** 1 of 3 ***
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2024 | EDWIN ESPIN |
| Plans on Hold | 11/26/2024 | CHIHARU SUZUKI |
| Hold Released | 12/4/2024 | CHIHARU SUZUKI |
| Re-Activate Applicaton | 12/4/2024 | CHIHARU SUZUKI |
| Corrections Issued | 12/18/2024 | EDWIN ESPIN |
| Quality Review Completed | 1/8/2025 | KAVIAN REFAHI |
| Building Plans Picked Up | 1/13/2025 | APPLICANT |
| Applicant returned to address corrections | 2/27/2025 | EDWIN ESPIN |
| Plan Check Approved | 3/21/2025 | EDWIN ESPIN |
| Issued | 4/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| Highway dedication | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| SB8 RUD | Cleared | 12/19/2024 | ALYSSA FLORES |
| Sewer availability | Cleared | 12/19/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 1/2/2025 | ERNEST TSE |
| Hydrant and Access approval | Cleared | 1/6/2025 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | BIAINA HARITUNIAN |
| Frnt yard landscape/Water mgmt | Cleared | 2/14/2025 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | May,, Philip S; Lic. No.: LA3104 | 60 VINTAGE RANCHO MIRAGE, CA 92270 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 6/13/2025 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 7/16/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 7/30/2025 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 7/30/2025 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 8/28/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/29/2025 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 9/26/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 10/7/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 10/7/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/14/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 10/21/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 10/21/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/21/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/6/2025 | Approved | JOSE AVILA |
| Shower Pan | 11/6/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/17/2025 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 11/17/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/17/2025 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 11/17/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/18/2025 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | JOSE AVILA |
| Insulation | 12/8/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 12/17/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Wood Frame | 12/19/2025 | No Access for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/23/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Final | 6/1/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/8/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/8/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/8/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/20/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/20/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/20/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/20/2026 | Approved | ROBERTO PALACIOS-LOPEZ |