409-409 1/2 E 99TH ST 90003

Certificate Information: 409-409 1/2 E 99TH ST 90003

Application / Permit
24010-30000-04701
Plan Check / Job No.
B24WL08887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
major remodeling of existing 1 story S.F.D. and addition + conversion to 2 story Duplex. *** 1 of 2 ***
Permit Issued
Issued on 2/13/2025
Issuing Office
Metro
Current Status
CofO Issued on 11/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 BEHROUZ KHOKHAR
Corrections Issued 11/25/2024 BEHROUZ KHOKHAR
Quality Review Completed 12/2/2024 CHIHARU SUZUKI
Applicant returned to address corrections 12/4/2024 BEHROUZ KHOKHAR
Building Plans Picked Up 12/4/2024 APPLICANT
Applicant returned to address corrections 1/29/2025 BEHROUZ KHOKHAR
Applicant returned to address corrections 2/4/2025 BEHROUZ KHOKHAR
Plan Check Approved 2/4/2025 BEHROUZ KHOKHAR
Issued 2/13/2025 APPLICANT
CofO in Progress 11/4/2025 ANTHONY EGSON
Permit Finaled 11/5/2025 ANSON MAGLASANG
CofO Issued 11/5/2025 ANSON MAGLASANG
Permit Finaled 11/5/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/17/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 12/17/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/19/2024 WALLIE JONG
Permit Cleared 2/4/2025 DAVID LOPEZ
Sewer availability Cleared 2/4/2025 ADRIAN SANCHEZ

Contact Information

Architect Hrd, Arch Inc.; Lic. No.: C35150 11620 WILSHIRE BLVD   SUITE 900    LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2025 Approved ANTHONY EGSON
PLUMBING-Rough 4/10/2025 Partial Approval EUGENE CASSIDY
Wood Frame 4/10/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Approval JOSEPH MCGARRY
Insulation 4/11/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval ANTHONY EGSON
Special/Order Compliance 6/13/2025 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/30/2025 Approved JOHN KLARIN
ELECTRICAL-Rough 6/30/2025 Approved JOHN KLARIN
Green Building Rough 6/30/2025 Approved JOHN KLARIN
HVAC-Rough 6/30/2025 Approved JOHN KLARIN
PLUMBING-Rough 6/30/2025 Approved JOHN KLARIN
Insulation 7/9/2025 Approved JOHN KLARIN
Drywall Nailing 8/6/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 8/6/2025 Approved ANTHONY EGSON
Underground Mechanical 8/28/2025 Approved ANTHONY EGSON
Sewer 8/29/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 10/14/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 10/14/2025 Corrections Issued ANTHONY EGSON
Drywall Nailing 10/15/2025 Approved ANTHONY EGSON
Final 10/15/2025 Corrections Issued ANTHONY EGSON
Green Building Final 10/15/2025 Approved ANTHONY EGSON
PLUMBING-Final 10/15/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 10/15/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 10/17/2025 Approved ANTHONY EGSON
Final 10/17/2025 Partial Approval ANTHONY EGSON
HVAC-Final 10/17/2025 Approved ANTHONY EGSON
Final 11/4/2025 OK to Issue CofO ANTHONY EGSON