5191 W 21ST ST 90016
Certificate Information: 5191 W 21ST ST 90016
- Application / Permit
- 24010-30000-04445
- Plan Check / Job No.
- B24WL08264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED TWO STORY DETACHED ADU PER STATE LAW (REAR BUILDING) ***BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT*** ---3 OF 3---
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Current Status
- Issued on 1/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 11/18/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/20/2024 | KEN GILL |
| Building Plans Picked Up | 11/26/2024 | APPLICANT |
| Plan Check Approved | 1/16/2025 | CRYSTEL MAALOUF |
| Issued | 1/16/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/18/2024 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 11/18/2024 | ENRIQUE ACOSTA |
| Address approval | Cleared | 11/25/2024 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | JILVER MAZARIEGOS |
| SB8 RUD | Cleared | 11/25/2024 | MICHAEL ZIRBES |
| Sewer availability | Cleared | 11/25/2024 | JILVER MAZARIEGOS |
| Low Impact Development (LID) | Cleared | 12/4/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/5/2024 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2025 | Approved | ARTHUR NEGRETE |
| Sewer | 3/4/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/26/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 7/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Rough | 7/11/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Approved | ARTHUR NEGRETE |
| Deputy Wood Construction | 7/25/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/30/2025 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 7/30/2025 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/30/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/6/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 8/6/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 8/6/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 9/3/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 9/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 9/16/2025 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 1/9/2026 | Partial Approval | BRENDAN MORELLI |
| Final | 5/4/2026 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 5/4/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Not Required | BRENDAN MORELLI |
| Smoke Detectors | 5/4/2026 | Approved | BRENDAN MORELLI |
| Final | 5/11/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 5/15/2026 | Corrections Issued | DAVID WILLIAMS |
| Service/Power Release | 5/15/2026 | Corrections Issued | DAVID WILLIAMS |