635 N BONHILL ROAD 90049

Certificate Information: 635 N BONHILL ROAD 90049

Application / Permit
24010-30000-04401
Plan Check / Job No.
B24WL08194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New detached rec room. with NFPA 13D sprinkler
Permit Issued
Issued on 4/3/2025
Issuing Office
West Los Angeles
Current Status
Issued on 4/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/18/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 KAVIAN REFAHI
Corrections Issued 10/26/2024 KAVIAN REFAHI
Quality Review Completed 11/4/2024 CHIHARU SUZUKI
Building Plans Picked Up 11/15/2024 APPLICANT
Applicant returned to address corrections 2/26/2025 KAVIAN REFAHI
Plan Check Approved 3/14/2025 KAVIAN REFAHI
Issued 4/3/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/26/2024 DARIN LAM
Miscellaneous Cleared 12/27/2024 RUBEN VASQUEZ
ZA Case Cleared 12/27/2024 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 2/5/2025 DARIN LAM
GPI Written Notices Cleared 3/14/2025 KAVIAN REFAHI
Grading Pre-Inspection Cleared 3/14/2025 KAVIAN REFAHI

Contact Information

Contractor Bespoke Builders; Lic. No.: 1107603-B 269 S. BEVERLY DRIVE #924      BEVERLY HILLS, CA 90212
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/27/2025 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 7/2/2025 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 8/22/2025 Not Ready for Inspection KEVIN SARGSYAN
Sewer 8/25/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/27/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/9/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 9/9/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 9/9/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 9/12/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 9/12/2025 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/12/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 10/21/2025 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/21/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 10/22/2025 Partial Approval KEVIN SARGSYAN
Green Building Rough 10/22/2025 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 10/22/2025 Partial Approval KEVIN SARGSYAN
Verify Sprinkler Sign Off 10/22/2025 Approved KEVIN SARGSYAN
Insulation 10/27/2025 Corrections Issued KEVIN SARGSYAN
Insulation 11/5/2025 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 11/14/2025 Partial Approval HERBERT GIRON
Insulation 11/18/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/18/2025 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 12/29/2025 Approved KEVIN SARGSYAN