2803-2805 S CARDIFF AVE 90034

Certificate Information: 2803-2805 S CARDIFF AVE 90034

Application / Permit
24010-30000-04352
Plan Check / Job No.
B24WL08075
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND JUNIOR ACCESSORY DWELLING UNIT (JADU) PER GCS 65852.2(e)(1)(A) AND 65852.22, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS
Permit Issued
Issued on 3/19/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 SERGIO SILVA
Corrections Issued 10/22/2024 SERGIO SILVA
Quality Review Completed 10/22/2024 KAVIAN REFAHI
Building Plans Picked Up 10/28/2024 APPLICANT
Applicant returned to address corrections 12/9/2024 SERGIO SILVA
Applicant returned to address corrections 3/3/2025 SERGIO SILVA
Applicant returned to address corrections 3/10/2025 SERGIO SILVA
Plan Check Approved 3/17/2025 SERGIO SILVA
Issued 3/19/2025 APPLICANT
CofO in Progress 6/3/2026 ASHLEY THOMPSON
Permit Finaled 6/4/2026 RICHARD STEINBACH
CofO Issued 6/4/2026 RICHARD STEINBACH
Permit Finaled 6/4/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/6/2024 ANTHONY MAINEZ
Permit Cleared 11/6/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/8/2024 ANTHONY MAINEZ
Sewer availability Cleared 11/8/2024 ANTHONY MAINEZ
Trees in Parkway Cleared 11/14/2024 MIGUEL ORNELAS
Low Impact Development (LID) Cleared 11/19/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/22/2024 ANTHONY MAINEZ
Hydrant and Access approval Cleared 2/23/2025 PATRICK PEREZ
Excavation more than 5-ft deep Cleared 3/3/2025 CALOSHA APPROVED
GPI Written Notices Cleared 3/3/2025 SERGIO SILVA
Grading Pre-Inspection Cleared 3/3/2025 SERGIO SILVA
Miscellaneous Cleared 3/3/2025 SERGIO SILVA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 200      ALISO VIEJO, CA 92656
Engineer Chrysostomo,, Anderson; Lic. No.: L9216 9592 ERSKINE DRIVE      HUNTINGTON BEACH, CA 92646
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025
Engineer Nguyen,, Huan; Lic. No.: C64238 15 STUDEBAKER      IRVINE, CA 92618
Engineer Toedter,, Randy; Lic. No.: S2991 689 COUNTY SQUARE DR UNIT 32      VENTURA, CA 93003

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/15/2025 Corrections Issued MEL KHACHATOURIAN
Underground Mechanical 9/15/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/16/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 9/16/2025 Approved MICHAEL ALLEN
Deputy Reinf. Concrete 10/1/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 10/2/2025 Approved EVAN COOPER
METHANE-Barrier 10/2/2025 Approved EVAN COOPER
METHANE-Subgrade 10/2/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 10/27/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 12/5/2025 Approved EVAN COOPER
ELECTRICAL-Rough 12/11/2025 Approved ASHLEY THOMPSON
HVAC-Rough 12/12/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 12/19/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 12/19/2025 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 1/2/2026 Partial Inspection DAVID FASTIGGI
Underground Mechanical 1/2/2026 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 1/12/2026 Approved ASHLEY THOMPSON
Green Building Rough 1/12/2026 Approved ASHLEY THOMPSON
Insulation 1/12/2026 Corrections Issued ASHLEY THOMPSON
METHANE-Rough 1/12/2026 Approved ASHLEY THOMPSON
Underground Mechanical 1/12/2026 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 1/12/2026 Approved ASHLEY THOMPSON
Drywall Nailing 1/21/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 1/28/2026 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 2/20/2026 Approved ASHLEY THOMPSON
Shower Pan 2/20/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Final 4/16/2026 Approved EVAN COOPER
Service/Power Release 4/16/2026 Approved EVAN COOPER
HVAC-Final 4/17/2026 Corrections Issued WILBER ROSALES
PLUMBING-Final 4/17/2026 Approved WILBER ROSALES
Final 5/28/2026 Corrections Issued ASHLEY THOMPSON
Green Building Final 5/28/2026 Approved ASHLEY THOMPSON
HVAC-Final 5/28/2026 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Not Required ASHLEY THOMPSON
Smoke Detectors 5/28/2026 Approved ASHLEY THOMPSON
Final 6/2/2026 OK to Issue CofO ASHLEY THOMPSON