7729 N WYNNE AVE 91335
Certificate Information: 7729 N WYNNE AVE 91335
- Application / Permit
- 24010-30000-04315
- Plan Check / Job No.
- B24WL07999
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(2).
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2024 | DAVID CASTILLO |
| Corrections Issued | 10/18/2024 | DAVID CASTILLO |
| Building Plans Picked Up | 10/21/2024 | APPLICANT |
| Applicant returned to address corrections | 4/7/2025 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/7/2025 | ROSENDO MEDINA |
| Issued | 5/19/2025 | APPLICANT |
| CofO in Progress | 10/14/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 10/23/2025 | JOHN JANSON |
| CofO Issued | 10/23/2025 | JOHN JANSON |
| Permit Finaled | 10/23/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/5/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/27/2024 | EDGAR ALCARAZ |
| Construction within easement | Cleared | 2/18/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 6/5/2025 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 6/12/2025 | Approved | ARUTYUN MADATYAN |
| Sewer | 6/24/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/30/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 6/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/28/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/28/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/28/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 8/21/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Rough | 8/21/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 8/21/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 8/21/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Insulation | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 8/26/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 8/29/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/6/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 10/6/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 10/6/2025 | Not Required | ARUTYUN MADATYAN |
| Smoke Detectors | 10/6/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/10/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/10/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 10/10/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/10/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | ARUTYUN MADATYAN |