3401-3403 S TILDEN AVE 90034

Certificate Information: 3401-3403 S TILDEN AVE 90034

Application / Permit
24010-30000-04165
Plan Check / Job No.
B24WL07626
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story Duplex at front . Fully equipped with fire sprinklered NFPA 13D
Permit Issued
Issued on 6/17/2025
Issuing Office
West Los Angeles
Current Status
Issued on 6/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 ALFREDO JARA
Corrections Issued 10/8/2024 ALFREDO JARA
Quality Review Completed 10/11/2024 CHIHARU SUZUKI
Building Plans Picked Up 10/17/2024 APPLICANT
Disabled Access Plans Picked Up 10/17/2024 APPLICANT
Plan Check Approved 6/9/2025 ALFREDO JARA
Issued 6/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/16/2024 DIANA RENTERIA
Permit Cleared 10/16/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 10/16/2024 DIANA RENTERIA
Sewer availability Cleared 10/16/2024 DIANA RENTERIA
Trees in Parkway Cleared 10/30/2024 MIGUEL ORNELAS
Specific Plan Cleared 11/25/2024 FREDDY GARCIA
Hydrant and Access approval Cleared 1/6/2025 JERRY KAO
Frnt yard landscape/Water mgmt Cleared 1/22/2025 NATHAN ROMINE
Low Impact Development (LID) Cleared 1/22/2025 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 1/30/2025 DIANA RENTERIA
ZI Cleared 5/19/2025 NATHAN ROMINE
Miscellaneous Cleared 6/5/2025 DIANA RENTERIA
Building over 36-ft Cleared 6/9/2025 CALOSHA APPROVED
GPI Written Notices Cleared 6/9/2025 ALFREDO JARA
Grading Pre-Inspection Cleared 6/9/2025 ALFREDO JARA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 8/14/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 8/18/2025 Approved KIRK SANDERS
Deputy Other (see comments) 8/19/2025 Conditional Approval CHRISTOPHER WILSON
Special/Order Compliance 8/25/2025 Corrections Issued KIRK SANDERS
Structural Steel Frame 8/25/2025 Conditional Approval KIRK SANDERS
Deputy Wood Construction 9/5/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Partial Approval ARAM AVEDISIAN
Structural Steel Frame 9/5/2025 Approved ARAM AVEDISIAN
Underground Mechanical 9/8/2025 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval JAYLIN GRAVITTE
Deputy Wood Construction 9/25/2025 Conditional Approval MICHAEL PELHAM
Underground Mechanical 9/25/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 10/16/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 11/13/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 11/14/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 12/1/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 12/1/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 12/4/2025 Conditional Approval MICHAEL ALLEN
Green Building Rough 12/4/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/4/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 12/4/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 12/4/2025 Partial Approval MICHAEL ALLEN
Insulation 12/5/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 12/5/2025 Partial Approval KIRK SANDERS
Insulation 12/9/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/10/2025 Approved KIRK SANDERS
Drywall Nailing 12/10/2025 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 12/10/2025 Approved KIRK SANDERS
Drywall Nailing 12/12/2025 Approved MICHAEL ALLEN
Shower Pan 12/15/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 12/24/2025 Approved ANDREW NAVE
ELECTRICAL-Final 4/28/2026 Approved EVAN COOPER
Service/Power Release 6/4/2026 Approved KIRK SANDERS
Gas Test 6/25/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 6/25/2026 Partial Approval ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV Approved ARAM AVEDISIAN
HVAC-Final 6/26/2026 Corrections Issued ANTHONY EGSON
Final 7/1/2026 Corrections Issued KIRK SANDERS
Green Building Final 7/1/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 7/1/2026 Approved KIRK SANDERS