11729 W HARTSOOK ST 91607
Certificate Information: 11729 W HARTSOOK ST 91607
- Application / Permit
- 24010-30000-04132
- Plan Check / Job No.
- B24WL07540
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-Story S.F.D. with attached garage and roof truss system. ***1 of 2***
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | DAVID CASTILLO |
| Corrections Issued | 10/7/2024 | DAVID CASTILLO |
| Quality Review Completed | 10/9/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/15/2024 | APPLICANT |
| Plan Check Approved | 2/10/2025 | DAVID CASTILLO |
| Issued | 2/10/2025 | APPLICANT |
| CofO in Progress | 10/31/2025 | JAVIER RAMOS JR |
| No Progress | 12/24/2025 | RAUL OLAGI |
| CofO in Progress | 12/24/2025 | RAUL OLAGI |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| CofO Issued | 2/17/2026 | RUBEN SALAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 10/24/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/24/2024 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 10/25/2024 | ALEX VELA |
| Trees in Parkway | Cleared | 11/6/2024 | MIGUEL ORNELAS |
| Specific Plan | Cleared | 11/7/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 11/7/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 11/7/2024 | JOANNA MARROQUIN |
| Permit | Cleared | 11/14/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 1/23/2025 | JERRY KAO |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 3/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 4/1/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/1/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/4/2025 | Approved | JAVIER RAMOS JR |
| Deputy Reinf. Concrete | 4/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 4/22/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 5/7/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/15/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/29/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/29/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/29/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/5/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/5/2025 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 6/25/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/17/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/29/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 8/20/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 9/24/2025 | Approved | JAVIER RAMOS JR |
| Final | 10/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 10/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/14/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Smoke Detectors | 10/14/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 10/16/2025 | Approved | RYAN SALAZAR |
| Final | 10/21/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/21/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 10/31/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 10/31/2025 | Approved | JAVIER RAMOS JR |