2236 S MIDVALE AVE 90064
Certificate Information: 2236 S MIDVALE AVE 90064
- Application / Permit
- 24010-30000-04131
- Plan Check / Job No.
- B24WL07537
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU WITH ROOF TRUSS per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d) AND (g) ---2 OF 3---
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- Current Status
- Issued on 7/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | BEHROUZ KHOKHAR |
| Corrections Issued | 10/10/2024 | BEHROUZ KHOKHAR |
| Quality Review Completed | 10/11/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/15/2024 | APPLICANT |
| Applicant returned to address corrections | 3/19/2025 | BEHROUZ KHOKHAR |
| Applicant returned to address corrections | 4/14/2025 | BEHROUZ KHOKHAR |
| Applicant returned to address corrections | 7/2/2025 | BEHROUZ KHOKHAR |
| Plan Check Approved | 7/23/2025 | BEHROUZ KHOKHAR |
| Issued | 7/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2024 | LIAM ODONOVAN |
| Low Impact Development (LID) | Cleared | 10/24/2024 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 10/25/2024 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 12/6/2024 | TINA MIRANDA |
| Specific Plan | Cleared | 1/24/2025 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 4/14/2025 | BEHROUZ KHOKHAR |
| Permit | Cleared | 4/18/2025 | VLADIMIR ARUTYUNYAN |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/11/2025 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 10/2/2025 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/2/2025 | Approved | MEL KHACHATOURIAN |
| Piling/Pier/Caisson | 10/2/2025 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 10/2/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 11/12/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 11/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 11/24/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 12/4/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 12/4/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 1/7/2026 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 1/7/2026 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 1/7/2026 | Approved | ASHLEY THOMPSON |
| Insulation | 1/15/2026 | Corrections Issued | KIRK SANDERS |
| Insulation | 1/23/2026 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 1/26/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/23/2026 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 2/23/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/16/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/22/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 5/28/2026 | Approved | ARAM AVEDISIAN |