2522 S AMHERST AVE 90064
Certificate Information: 2522 S AMHERST AVE 90064
- Application / Permit
- 24010-30000-03947
- Plan Check / Job No.
- B24WL07217
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (24) State Approved Dwelling/Mobile Home
- Work Description
- New 2-story single family home w/ att. garage. Sprinklered through out
- Permit Issued
- Issued on 7/16/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 10/4/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 10/10/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/10/2024 | APPLICANT |
| Applicant returned to address corrections | 10/23/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 6/12/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 6/18/2025 | HOOMAN HAJIZADEH |
| Issued | 7/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2024 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | VLADIMIR ARUTYUNYAN |
| Permit | Cleared | 10/30/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 10/30/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 10/30/2024 | VLADIMIR ARUTYUNYAN |
| Trees in Parkway | Cleared | 12/4/2024 | MIGUEL ORNELAS |
| Hydrant and Access approval | Cleared | 1/21/2025 | KURT CORRAL |
| Specific Plan | Cleared | 1/23/2025 | FREDDY GARCIA |
Contact Information
| Architect | Bica,, Alex Stephan; Lic. No.: C40375 | 3019 OCEAN PARK BLVD #714 SANTA MONICA, CA 90405 |
| Contractor | Bica Build; Lic. No.: 1123041-B | 11414 FRANCIS PL LOS ANGELES, CA 90066 |
| Engineer | Powers,, Jason R; Lic. No.: C76130 | 10336 BADGER LN TRUCKEE, CA 96161 |
| Engineer | Russell,, Robert Taylor; Lic. No.: C84132 | 1750 N HARVARD BLVD APT 109 LOS ANGELES, CA 90027 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Voorheis,, Jeff; Lic. No.: L7570 | 17049 SUNBURST ST SHERWOOD FOREST, CA 91325 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/6/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 8/29/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/3/2025 | Partial Approval | KIRK SANDERS |
| Deputy Other (see comments) | 9/16/2025 | Conditional Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 9/16/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 9/24/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/6/2025 | Corrections Issued | KIRK SANDERS |
| Wood Frame | 10/6/2025 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 10/8/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 10/9/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Conditional Approval | KIRK SANDERS |
| Insulation | 10/10/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 10/20/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Partial Approval | KIRK SANDERS |
| Wood Frame | 12/23/2025 | No Access for Inspection | RUBEN RIVAS |
| HVAC-Rough | 2/5/2026 | Partial Inspection | RYAN SALAZAR |
| Sewer | 2/13/2026 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 2/13/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/20/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/18/2026 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2026 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 3/18/2026 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/23/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | RYAN SALAZAR |
| Green Building Rough | 4/1/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/1/2026 | Partial Approval | RYAN SALAZAR |
| MERV13>=Rough | 4/1/2026 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 4/1/2026 | Approved | RYAN SALAZAR |
| Insulation | 4/7/2026 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | EVAN COOPER |
| Insulation | 4/17/2026 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/23/2026 | Approved | EUGENE CASSIDY |