10545 W DUNLEER DR 90064

Certificate Information: 10545 W DUNLEER DR 90064

Application / Permit
24010-30000-03935
Plan Check / Job No.
B24WL07173
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-Story Detached ADU per GC 66323(a)(2)
Permit Issued
Issued on 3/14/2025
Issuing Office
Current Status
Issued on 3/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 KAVIAN REFAHI
Corrections Issued 9/21/2024 KAVIAN REFAHI
Quality Review Completed 9/25/2024 CHIHARU SUZUKI
Building Plans Picked Up 9/26/2024 APPLICANT
Applicant returned to address corrections 2/5/2025 KAVIAN REFAHI
Plan Check Approved 3/7/2025 KAVIAN REFAHI
Issued 3/14/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 10/8/2024 SARAH YOUSSEF
Address approval Cleared 10/9/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/9/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 10/9/2024 KIMBERLY HERNANDEZ
Hydrant and Access approval Cleared 12/19/2024 JERRY KAO
Construction near power lines Cleared 1/15/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 1/25/2025 LIAM ODONOVAN
Specific Plan Cleared 1/27/2025 RICHARD WOO
GPI Written Notices Cleared 2/5/2025 KAVIAN REFAHI
Grading Pre-Inspection Cleared 2/5/2025 KAVIAN REFAHI

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 200      ALISO VIEJO, CA 92656
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nguyen,, Huan; Lic. No.: C64238 15 STUDEBAKER      IRVINE, CA 92618
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/20/2025 Partial Approval ASHLEY THOMPSON
Sewer 8/20/2025 Approved ASHLEY THOMPSON
Underground Mechanical 8/20/2025 Partial Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 8/29/2025 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 8/29/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Not Ready for Inspection JAYLIN GRAVITTE
Deputy Wood Construction 10/21/2025 Conditional Approval KIRK SANDERS
Underground Mechanical 10/21/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 10/28/2025 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 10/28/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Approved STEPHANIE SWANSON
HVAC-Rough 11/19/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 12/4/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 12/4/2025 Approved ASHLEY THOMPSON
Light Gage Steel Frame 12/4/2025 Approved ASHLEY THOMPSON
MERV13>=Rough 12/4/2025 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 12/4/2025 Approved ASHLEY THOMPSON
Wood Frame 12/4/2025 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 2/23/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/23/2026 Partial Approval RYAN SALAZAR
Insulation 3/4/2026 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 3/13/2026 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/17/2026 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 3/20/2026 Approved ASHLEY THOMPSON
Insulation 3/20/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/28/2026 Approved ASHLEY THOMPSON
Shower Pan 4/28/2026 Approved ASHLEY THOMPSON