3608-3608 1/2 S 10TH AVE 90018

Certificate Information: 3608-3608 1/2 S 10TH AVE 90018

Application / Permit
24010-30000-03777
Plan Check / Job No.
B24WL06892
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2-story Duplex per SB-9 *** 1 of 2 ***
Permit Issued
Issued on 10/28/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 KAVIAN REFAHI
Corrections Issued 9/14/2024 KAVIAN REFAHI
Quality Review Completed 9/23/2024 CHIHARU SUZUKI
Building Plans Picked Up 9/25/2024 APPLICANT
Plan Check Approved 10/28/2024 KAVIAN REFAHI
Issued 10/28/2024 APPLICANT
CofO in Progress 7/24/2025 JUSTIN HAWLEY
CofO Issued 7/25/2025 DEROLD HAUFF
Permit Finaled 7/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/17/2024 TREVOR QUAN
Sewer availability Cleared 9/17/2024 TREVOR QUAN
Low Impact Development (LID) Cleared 9/19/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/3/2024 WALLIE JONG
Senate Bill 9 Cleared 10/11/2024 JAZMIN ROQUE
ZA Case Cleared 10/11/2024 JAZMIN ROQUE
ZA Case Cleared 10/11/2024 JAZMIN ROQUE
ZA Case Cleared 10/11/2024 JAZMIN ROQUE
Hydrant and Access approval Cleared 10/15/2024 JOHN CONNEALLY

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Vip Construction 1 Inc; Lic. No.: 1097925-B 11038 BENWELL DRIVE APT D      LYNWOOD, CA 90262
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/5/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 11/13/2024 Approved JOHN QUINTANILLA
Sewer 11/13/2024 Partial Approval JOHN QUINTANILLA
Footing/Foundation/Slab 11/22/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Approved JUSTIN HAWLEY
PLUMBING-Rough 2/7/2025 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Rough 2/11/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 2/12/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 2/21/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/5/2025 Approved ENRIQUE MIRELES
Green Building Rough 3/5/2025 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 3/5/2025 Approved ENRIQUE MIRELES
Wood Frame 3/5/2025 Approved ENRIQUE MIRELES
Insulation 3/20/2025 Corrections Issued JEFFREY MEAD
Insulation 3/25/2025 Approved JEFFREY MEAD
Drywall Nailing 4/3/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 4/3/2025 Approved JOSH MEISTER
PLUMBING-Rough 5/14/2025 Not Ready for Inspection RONNIE MINDANAO
Sewer 5/15/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/4/2025 Not Ready for Inspection JUSTIN HAWLEY
Final 6/4/2025 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Final 7/7/2025 Approved JUSTIN HAWLEY
Final 7/7/2025 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 7/7/2025 Approved JUSTIN HAWLEY
HVAC-Final 7/7/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 7/7/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Not Required JUSTIN HAWLEY
Service/Power Release 7/7/2025 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 7/7/2025 Approved JUSTIN HAWLEY
Final 7/24/2025 OK to Issue CofO JUSTIN HAWLEY
Service/Power Release 7/24/2025 Approved JUSTIN HAWLEY