2044-2048 S GLENCOE AVE 90291
Certificate Information: 2044-2048 S GLENCOE AVE 90291
- Application / Permit
- 24010-30000-03450
- Plan Check / Job No.
- B24WL06217
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Addition to and conversion of (E) SFD w/ attched garage & recroom into a duplex per SB-9 unit with an attached 2-car garage and ADU per Ordinance LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 5/14/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 9/3/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 9/13/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/13/2024 | APPLICANT |
| Applicant returned to address corrections | 1/27/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 4/25/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 5/6/2025 | HOOMAN HAJIZADEH |
| Issued | 5/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2024 | ANTHONY MAINEZ |
| Low Impact Development (LID) | Cleared | 10/10/2024 | MITESH PATEL |
| Sewer availability | Cleared | 10/10/2024 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 12/2/2024 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 12/8/2024 | PATRICK PEREZ |
| Senate Bill 9 | Cleared | 3/19/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 3/20/2025 | MAX LODER |
| Miscellaneous | Cleared | 3/20/2025 | MAX LODER |
| Roof/Waste drainage to street | Cleared | 4/5/2025 | LIAM ODONOVAN |
| SB8 RUD | Cleared | 4/21/2025 | MICHAEL ZIRBES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 7/23/2026 |
Inspection Request History
| PLUMBING-Rough | 7/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 7/25/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 7/30/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/18/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 9/23/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | No Access for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 11/19/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 11/19/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 1/14/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 2/13/2026 | Approved | RUBEN RIVAS |
| Insulation | 2/26/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/9/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 3/11/2026 | Approved | RUBEN RIVAS |
| Green Building Rough | 3/11/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Not Ready | RUBEN RIVAS |