2531 W 12TH ST 1-2 90006

Certificate Information: 2531 W 12TH ST 1-2 90006

Application / Permit
24010-30000-03415
Plan Check / Job No.
B24WL06083
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-Story Duplex A w/Attached Rec.Room,NFPA 13D-Fire Sprinklers Throughout ** 1 of 3 **
Permit Issued
Issued on 2/6/2025
Issuing Office
Metro
Current Status
Issued on 2/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 DAVID CASTILLO
Corrections Issued 8/20/2024 DAVID CASTILLO
Quality Review Completed 9/1/2024 KAVIAN REFAHI
Building Plans Picked Up 9/4/2024 APPLICANT
Plan Check Approved 12/18/2024 DAVID CASTILLO
Issued 2/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/20/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 8/20/2024 WALLIE JONG
SB8 RUD Cleared 8/20/2024 DAVID CASTILLO
Eng Process Fee Ord 176,300 Cleared 8/21/2024 WALLIE JONG
Hold Cleared 8/22/2024 MARIA VENDIVIL
Frnt yard landscape/Water mgmt Cleared 8/27/2024 MAYELA VILLA
Permit Cleared 8/30/2024 CELINA MORENO
Sewer availability Cleared 8/30/2024 CELINA MORENO
Low Impact Development (LID) Cleared 9/5/2024 ORVAL HERNANDEZ-MARCI
Highway dedication Cleared 9/9/2024 TREVOR QUAN
Trees in Parkway Cleared 9/16/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 12/9/2024 GILBERT URREA

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD BLVD # 900      LOS ANGELES, CA 90064
Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880
Engineer Toufighi,, Pejman; Lic. No.: M31480 22346 BARCOTTA DRIVE      SANTA CLARITA, CA 91350

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2025 Partial Approval WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 4/8/2025 Approved WILLIAM SIERRA
Footing/Foundation/Slab 4/8/2025 Approved WILLIAM SIERRA
METHANE-Barrier 4/8/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 4/8/2025 Approved WILLIAM SIERRA
Sewer 4/22/2025 No Access for Inspection WILLIAM SIERRA
Sewer 4/24/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Not Ready for Inspection WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 No Access for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Partial Approval WILLIAM SIERRA
Deputy Wood Construction 7/22/2025 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/21/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Rough 8/21/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 8/26/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Rough 8/26/2025 Corrections Issued WILLIAM SIERRA
Interior/Exterior Lathing 8/26/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 9/11/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 9/11/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 9/11/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Rough 9/15/2025 Approved HAMIK HARTOUNIAN
Gas Test 9/30/2025 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 9/30/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 10/6/2025 Partial Approval WILLIAM SIERRA
BUILDING-Rough-Frame 10/21/2025 Corrections Issued WILLIAM SIERRA
Green Building Rough 10/21/2025 Approved WILLIAM SIERRA
METHANE-Rough 10/21/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 10/21/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 10/21/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 10/24/2025 Approved WILLIAM SIERRA
Insulation 11/10/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 11/10/2025 Approved DEVON JACKSON
Shower Pan 11/10/2025 Approved DEVON JACKSON
Special/Order Compliance 11/17/2025 Partial Inspection ALEX COLIN
Drywall Nailing 11/21/2025 Approved WILLIAM SIERRA
Underground Mechanical 1/27/2026 Approved WILLIAM SIERRA
Underground Mechanical 3/2/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Underground Mechanical 3/6/2026 Partial Approval WILLIAM SIERRA
ELECTRICAL-Final 5/22/2026 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Final 6/5/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Final 6/5/2026 Approved HAMIK HARTOUNIAN
Final 6/12/2026 Corrections Issued WILLIAM SIERRA
Green Building Final 6/12/2026 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 6/12/2026 SGSOV Approved WILLIAM SIERRA
Service/Power Release 6/12/2026 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 6/12/2026 Approved WILLIAM SIERRA