509 N MANSFIELD AVE 90036

Certificate Information: 509 N MANSFIELD AVE 90036

Application / Permit
24010-30000-03223
Plan Check / Job No.
B24WL05711
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH BASEMENT. ---2 OF 6---
Permit Issued
Issued on 3/21/2025
Issuing Office
West Los Angeles
Current Status
Issued on 3/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 KAVIAN REFAHI
Plans on Hold 8/8/2024 CHIHARU SUZUKI
Hold Released 8/16/2024 KAVIAN REFAHI
Corrections Issued 8/17/2024 KAVIAN REFAHI
Quality Review Completed 8/26/2024 CHIHARU SUZUKI
Building Plans Picked Up 8/27/2024 APPLICANT
Applicant returned to address corrections 9/23/2024 KAVIAN REFAHI
Applicant returned to address corrections 12/13/2024 KAVIAN REFAHI
Applicant returned to address corrections 2/24/2025 KAVIAN REFAHI
Plan Check Approved 3/7/2025 KAVIAN REFAHI
Issued 3/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/16/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/17/2024 DAVID LOPEZ
Sewer availability Cleared 9/17/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 11/14/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/25/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 12/4/2024 JERRY KAO
Excavation more than 5-ft deep Cleared 3/7/2025 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Allen; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2025 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/17/2025 Partial Approval CRAIG VAUGHAN
METHANE-Barrier 7/17/2025 Partial Approval CRAIG VAUGHAN
METHANE-Subgrade 7/17/2025 Partial Approval CRAIG VAUGHAN
Deputy Shotcrete 7/31/2025 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 7/31/2025 Partial Approval CRAIG VAUGHAN
METHANE-Barrier 7/31/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 7/31/2025 Not Ready for Inspection CRAIG VAUGHAN
Reinforced Concrete Frame 7/31/2025 Partial Approval CRAIG VAUGHAN
Deputy Shotcrete 8/5/2025 Conditional Approval CRAIG VAUGHAN
METHANE-Subgrade 8/20/2025 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/2/2025 Approved BRIAN SULLIVAN
METHANE-Barrier 9/2/2025 Approved BRIAN SULLIVAN
Wood Frame 9/16/2025 Partial Approval CRAIG VAUGHAN
Wood Frame 9/30/2025 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 11/26/2025 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Approved BRIAN SULLIVAN
Green Building Rough 1/20/2026 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 1/20/2026 Corrections Issued BRIAN SULLIVAN
METHANE-Final 1/20/2026 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 1/20/2026 Approved BRIAN SULLIVAN
PLUMBING-Rough 1/20/2026 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 1/20/2026 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/23/2026 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/23/2026 Approved CRAIG VAUGHAN
Green Building Rough 1/23/2026 Approved CRAIG VAUGHAN
HVAC-Rough 1/23/2026 Approved CRAIG VAUGHAN
METHANE-Rough 1/23/2026 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/6/2026 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/6/2026 Partial Approval CRAIG VAUGHAN
Insulation 2/26/2026 Approved CRAIG VAUGHAN
Shower Pan 2/26/2026 Approved CRAIG VAUGHAN
Drywall Nailing 3/11/2026 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/11/2026 Approved CRAIG VAUGHAN