5755 N FULCHER AVE 1 - 3 91601

Certificate Information: 5755 N FULCHER AVE 1 - 3 91601

Application / Permit
24010-30000-03158
Plan Check / Job No.
B24WL05529
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story duplex (B) (3,160 sf) w./ att. ADU (1,650 sf) and 2-car carport (660 sf) at rear of the lot per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 10/29/2024
Issuing Office
Metro
Current Status
Issued on 10/29/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 REZA HAGHIGHAT
Corrections Issued 8/3/2024 REZA HAGHIGHAT
Plans on Hold 8/8/2024 CHIHARU SUZUKI
Hold Released 8/12/2024 CHIHARU SUZUKI
Quality Review Completed 8/12/2024 CHIHARU SUZUKI
Building Plans Picked Up 8/12/2024 APPLICANT
Plan Check Approved 10/28/2024 REZA HAGHIGHAT
Issued 10/29/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/6/2024 EDGAR ALCARAZ
Highway dedication Cleared 8/6/2024 EDGAR ALCARAZ
Permit Cleared 8/6/2024 EDGAR ALCARAZ
Low Impact Development Cleared 8/7/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 8/13/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 8/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/13/2024 EDGAR ALCARAZ
Frnt yard landscape/Water mgmt Cleared 8/22/2024 ALEX VELA
Hydrant and Access approval Cleared 8/30/2024 LAVEON RIDER
SB8 RUD Cleared 10/4/2024 OLIVIA JIN
DAS Clearance Cleared 10/21/2024 REZA HAGHIGHAT

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2024 Approved JOSE AVILA
Underground Mechanical 11/6/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 11/13/2024 Approved JOSE AVILA
Deputy Reinf. Concrete 11/14/2024 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 1/21/2025 Conditional Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/14/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/14/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/19/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/20/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/27/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 6/26/2025 Approved RAUL OLAGI
Underground Mechanical 6/26/2025 Corrections Issued RAUL OLAGI
Underground Mechanical 7/2/2025 Approved ROBERTO PALACIOS-LOPEZ