10545 W BRADBURY ROAD 90064
Certificate Information: 10545 W BRADBURY ROAD 90064
- Application / Permit
- 24010-30000-03085
- Plan Check / Job No.
- B24WL05429
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) detached ADU per State Law GC 66323(a)(2)
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 8/14/2024 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 8/22/2024 | APPLICANT |
| Quality Review Completed | 8/24/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/25/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 4/29/2025 | HOOMAN HAJIZADEH |
| Issued | 5/6/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/9/2024 | OSCAR CASTRO |
| Address approval | Cleared | 3/8/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | DARIN LAM |
| Sewer availability | Cleared | 3/10/2025 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 3/26/2025 | MARCO SANCHEZ |
| Specific Plan | Cleared | 4/9/2025 | JOSHUA JONES |
| Roof/Waste drainage to street | Cleared | 4/15/2025 | COLIN LOREDO |
| GPI Written Notices | Cleared | 4/29/2025 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 4/29/2025 | HOOMAN HAJIZADEH |
Contact Information
| Contractor | G E Builders Inc; Lic. No.: 932264-B | 22312 KINZIE STREET CHATSWORTH, CA 91311 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Garciamontes,, Gerardo; Lic. No.: L9195 | 517 E WILSON AVENUE, STE. 102 GLENDALE, CA 91206 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Geologist | Daugherty,, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/8/2025 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 8/8/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/18/2025 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 8/18/2025 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 8/28/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/28/2025 | Partial Approval | ASHLEY THOMPSON |
| Underground Mechanical | 8/28/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Sewer | 1/13/2026 | Partial Approval | MICHAEL ALLEN |
| Underground Mechanical | 1/13/2026 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 1/20/2026 | Corrections Issued | ASHLEY THOMPSON |
| Sewer | 1/26/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/28/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 2/2/2026 | Not Ready for Inspection | WILBER ROSALES |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/5/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Insulation | 5/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/20/2026 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/20/2026 | Approved | CARLOS MATAMOROS |
| Insulation | 5/20/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/20/2026 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 5/22/2026 | Approved | ASHLEY THOMPSON |
| Insulation | 5/22/2026 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 6/2/2026 | Approved | ASHLEY THOMPSON |