5814 N BECK AVE 1-3 91601
Certificate Information: 5814 N BECK AVE 1-3 91601
- Application / Permit
- 24010-30000-02887
- Plan Check / Job No.
- B24WL01479
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-Story Duplex w/ Attached Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (e) at rear of the lot. No parking required per AB 2097: Reduced Parking Areas *** 1 of 2 ***
- Permit Issued
- Issued on 12/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | EDWIN ESPIN |
| Corrections Issued | 8/6/2024 | EDWIN ESPIN |
| Quality Review Completed | 8/19/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/22/2024 | APPLICANT |
| Applicant returned to address corrections | 8/30/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/13/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/20/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 12/4/2024 | EDWIN ESPIN |
| Plan Check Approved | 12/6/2024 | EDWIN ESPIN |
| Issued | 12/20/2024 | APPLICANT |
| CofO in Progress | 12/4/2025 | JAVIER RAMOS JR |
| Permit Finaled | 1/14/2026 | RUBEN SALAS |
| CofO Issued | 1/14/2026 | RUBEN SALAS |
| Permit Finaled | 1/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 8/8/2024 | CARLOS RAMIREZ |
| Low Impact Development (LID) | Cleared | 8/9/2024 | SARAH YOUSSEF |
| Highway dedication | Cleared | 9/3/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 9/3/2024 | CARLOS RAMIREZ |
| "Q" conditions | Cleared | 10/3/2024 | NATHAN ROMINE |
| SB8 RUD | Cleared | 10/7/2024 | LOUIE MILLER |
| Hydrant and Access approval | Cleared | 10/24/2024 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 10/25/2024 | NATHAN ROMINE |
| DAS Clearance | Cleared | 11/14/2024 | EDWIN ESPIN |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD #900 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 1/7/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 1/9/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/14/2025 | Approved | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 1/15/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 2/4/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/4/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 2/19/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 2/19/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 3/6/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 3/6/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/12/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 5/12/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/12/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/12/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/3/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/3/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/3/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/3/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/6/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/16/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/16/2025 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 8/26/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 8/26/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 8/29/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/2/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/5/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/5/2025 | Partial Approval | JAVIER RAMOS JR |
| Green Building Final | 11/19/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/19/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/19/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/3/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/3/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 12/3/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/3/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/8/2025 | Approved | JAVIER RAMOS JR |