5814 N BECK AVE 1-3 91601

Certificate Information: 5814 N BECK AVE 1-3 91601

Application / Permit
24010-30000-02887
Plan Check / Job No.
B24WL01479
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-Story Duplex w/ Attached Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (e) at rear of the lot. No parking required per AB 2097: Reduced Parking Areas *** 1 of 2 ***
Permit Issued
Issued on 12/20/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 EDWIN ESPIN
Corrections Issued 8/6/2024 EDWIN ESPIN
Quality Review Completed 8/19/2024 KAVIAN REFAHI
Building Plans Picked Up 8/22/2024 APPLICANT
Applicant returned to address corrections 8/30/2024 EDWIN ESPIN
Applicant returned to address corrections 11/13/2024 EDWIN ESPIN
Applicant returned to address corrections 11/20/2024 EDWIN ESPIN
Applicant returned to address corrections 12/4/2024 EDWIN ESPIN
Plan Check Approved 12/6/2024 EDWIN ESPIN
Issued 12/20/2024 APPLICANT
CofO in Progress 12/4/2025 JAVIER RAMOS JR
Permit Finaled 1/14/2026 RUBEN SALAS
CofO Issued 1/14/2026 RUBEN SALAS
Permit Finaled 1/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/8/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 8/8/2024 CARLOS RAMIREZ
Sewer availability Cleared 8/8/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 8/9/2024 SARAH YOUSSEF
Highway dedication Cleared 9/3/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 9/3/2024 CARLOS RAMIREZ
"Q" conditions Cleared 10/3/2024 NATHAN ROMINE
SB8 RUD Cleared 10/7/2024 LOUIE MILLER
Hydrant and Access approval Cleared 10/24/2024 KURT CORRAL
Frnt yard landscape/Water mgmt Cleared 10/25/2024 NATHAN ROMINE
DAS Clearance Cleared 11/14/2024 EDWIN ESPIN

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD BLVD   #900    LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/7/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 1/7/2025 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 1/9/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/14/2025 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 1/15/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 2/4/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 2/4/2025 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/4/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 2/19/2025 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/19/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 3/6/2025 Partial Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/6/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/1/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 5/12/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/12/2025 Approved JAVIER RAMOS JR
HVAC-Rough 5/12/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/12/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/21/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Approved JAVIER RAMOS JR
Insulation 6/3/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 6/3/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/3/2025 Approved JAVIER RAMOS JR
Shower Pan 6/3/2025 Approved JAVIER RAMOS JR
Insulation 6/6/2025 Approved JAVIER RAMOS JR
Drywall Nailing 6/16/2025 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 6/16/2025 Approved JAVIER RAMOS JR
Pre-Inspection 8/26/2025 Approved JAVIER RAMOS JR
Sewer 8/26/2025 Approved JAVIER RAMOS JR
Underground Mechanical 8/29/2025 Approved RYAN SALAZAR
Underground Mechanical 9/2/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/5/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 11/5/2025 Partial Approval JAVIER RAMOS JR
Green Building Final 11/19/2025 Approved JAVIER RAMOS JR
HVAC-Final 11/19/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 11/19/2025 Approved JAVIER RAMOS JR
Drywall Nailing 12/3/2025 Approved JAVIER RAMOS JR
Final 12/3/2025 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 12/3/2025 Approved JAVIER RAMOS JR
Smoke Detectors 12/3/2025 Approved JAVIER RAMOS JR
Service/Power Release 12/8/2025 Approved JAVIER RAMOS JR