5209 1/4-3/4 W 20TH ST 90016

Certificate Information: 5209 1/4-3/4 W 20TH ST 90016

Application / Permit
24010-30000-02803
Plan Check / Job No.
B24WL01427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 3-story sf SFD w/ attached ADU and carport **3 of 3** ** ADU Per LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO Issued on 1/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 ZENA HADDIS
Corrections Issued 8/9/2024 ZENA HADDIS
Re-Submittal Required 8/24/2024 KAVIAN REFAHI
Re-Submitted 9/4/2024 ZENA HADDIS
Corrections Issued 2 9/4/2024 KAVIAN REFAHI
Building Plans Picked Up 9/5/2024 APPLICANT
Submitted for Second Quality Review 11/6/2024 ZENA HADDIS
Quality Review Completed 11/6/2024 CHIHARU SUZUKI
Plan Check Approved 11/6/2024 ZENA HADDIS
Issued 11/7/2024 APPLICANT
CofO in Progress 1/14/2026 BRENDAN MORELLI
Permit Finaled 1/14/2026 DEROLD HAUFF
CofO Issued 1/14/2026 DEROLD HAUFF
Permit Finaled 1/14/2026 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 8/5/2024 BLAKE BOULIGNY
Address approval Cleared 8/8/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 8/8/2024 JILVER MAZARIEGOS
Low Impact Development (LID) Cleared 8/9/2024 SARAH YOUSSEF
Highway dedication Cleared 8/26/2024 KHAING AYE
Construction near power lines Cleared 8/27/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/4/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 9/4/2024 KHAING AYE
Sewer availability Cleared 9/4/2024 KHAING AYE
Opn space landscape/Water mgmt Cleared 11/4/2024 GEORGIA SMITH
Opn space landscape/Water mgmt Cleared 11/4/2024 GEORGIA SMITH
Hydrant and Access approval Cleared 11/6/2024 RUEL COLE

Contact Information

Architect , ; Lic. No.: C35150       ,
Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/26/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/6/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 2/21/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 3/7/2025 Partial Approval ARTHUR NEGRETE
ELECTRICAL-Rough 3/11/2025 Corrections Issued ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/19/2025 Approved ARTHUR NEGRETE
HVAC-Rough 3/19/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Rough 4/15/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 4/18/2025 Approved ARTHUR NEGRETE
Green Building Rough 4/18/2025 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 4/18/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/2/2025 Partial Approval ALEX COLIN
Insulation 5/13/2025 Approved ARTHUR NEGRETE
Drywall Nailing 6/2/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/10/2025 Approved ARTHUR NEGRETE
Shower Pan 6/10/2025 Approved ARTHUR NEGRETE
Underground Mechanical 9/2/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Not Ready WILLIAM SIERRA
ELECTRICAL-Final 11/19/2025 Corrections Issued ARTHUR NEGRETE
Final 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 11/19/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 11/19/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 11/19/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 11/20/2025 Approved ARTHUR NEGRETE
HVAC-Final 11/20/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 11/20/2025 Approved ARTHUR NEGRETE
Pre-Inspection 11/20/2025 Approved ARTHUR NEGRETE
Service/Power Release 11/20/2025 Approved ARTHUR NEGRETE
Final 12/1/2025 Corrections Issued BRENDAN MORELLI
Final 12/4/2025 Not Ready for Inspection BRENDAN MORELLI
Final 12/8/2025 Corrections Issued BRENDAN MORELLI
Final 12/11/2025 Corrections Issued BRENDAN MORELLI
Final 12/17/2025 Not Ready for Inspection BRENDAN MORELLI
Final 1/2/2026 Not Ready for Inspection BRENDAN MORELLI
Final 1/7/2026 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 1/7/2026 Not Ready for Inspection BRENDAN MORELLI
Final 1/9/2026 Not Ready for Inspection BRENDAN MORELLI
Final 1/13/2026 OK to Issue CofO BRENDAN MORELLI
Green Building Final 1/13/2026 Approved BRENDAN MORELLI