14422 W TIARA ST 91401
Certificate Information: 14422 W TIARA ST 91401
- Application / Permit
- 24010-30000-02768
- Plan Check / Job No.
- B24WL01409
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3-story Duplex A and attached rec room in front w/ steel columns & G.B. *** 1 of 2 ***
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | ZENA HADDIS |
| Corrections Issued | 7/25/2024 | ZENA HADDIS |
| Quality Review Completed | 7/26/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 7/26/2024 | APPLICANT |
| Plan Check Approved | 10/16/2024 | ZENA HADDIS |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 1/7/2026 | RYAN SALAZAR |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
| CofO Issued | 1/10/2026 | RUBEN SALAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/18/2024 | SARAH YOUSSEF |
| Address approval | Cleared | 7/19/2024 | BIAINA HARITUNIAN |
| Highway dedication | Cleared | 7/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| "Q" conditions | Cleared | 7/31/2024 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 7/31/2024 | RUBEN VASQUEZ |
| SB8 RUD | Cleared | 8/1/2024 | ALYSSA FLORES |
| Hydrant and Access approval | Cleared | 10/10/2024 | JOHN CONNEALLY |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Toufighi,, Pejman; Lic. No.: M31480 | 22346 BARCOTTA DRIVE SANTA CLARITA, CA 91350 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/9/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 12/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/24/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | RYAN SALAZAR |
| Special/Order Compliance | 1/14/2025 | Partial Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 4/14/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/14/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/2/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/2/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 5/2/2025 | Approved | RYAN SALAZAR |
| Insulation | 5/8/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/8/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 5/21/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/5/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 6/5/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/2/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/22/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 12/22/2025 | Approved | RYAN SALAZAR |
| Final | 12/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 12/24/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 12/24/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 12/24/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 12/24/2025 | Approved | RYAN SALAZAR |
| Final | 1/2/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 1/2/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 1/7/2026 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 1/7/2026 | Approved | RYAN SALAZAR |