110 N ROCKINGHAM AVE 90049

Certificate Information: 110 N ROCKINGHAM AVE 90049

Application / Permit
24010-30000-02593
Plan Check / Job No.
B24WL01321
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
new detached 4-car garage w/ RBS moment frames and grade beams *** 1 of 2 ***
Permit Issued
Issued on 9/30/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 6/20/2024 KAVIAN REFAHI
Corrections Issued 6/23/2024 KAVIAN REFAHI
Quality Review Completed 6/26/2024 REZA HAGHIGHAT
Building Plans Picked Up 6/28/2024 APPLICANT
Plan Check Approved 9/23/2024 KAVIAN REFAHI
Issued 9/30/2024 APPLICANT
CofO in Progress 12/1/2025 KEVIN SARGSYAN
Permit Finaled 12/3/2025 RICHARD STEINBACH
CofO Issued 12/3/2025 RICHARD STEINBACH
Permit Finaled 12/3/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/10/2024 LIAM ODONOVAN
Miscellaneous Cleared 7/11/2024 JACQUELINE TORRES
ZA Case Cleared 7/11/2024 JACQUELINE TORRES
Eng Process Fee Ord 176,300 Cleared 7/22/2024 VLADIMIR ARUTYUNYAN
Hydrant and Access approval Cleared 9/4/2024 JOHN CONNEALLY
GPI Written Notices Cleared 9/23/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 9/23/2024 KAVIAN REFAHI

Contact Information

Architect Brunn,, Dan; Lic. No.: C31368 737 S LONGWOOD AVENUE      LOS ANGELES, CA 90005
Contractor Owner-Builder       ,
Engineer Mercado,, Lizandro; Lic. No.: S4331 27240 TURNBERRY LN STE 200      VALENCIA, CA 91355

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2024 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/10/2025 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/11/2025 Partial Approval KEVIN SARGSYAN
Deputy Steel/Welding 3/3/2025 Conditional Approval KEVIN SARGSYAN
Deputy Steel/Welding 3/5/2025 Conditional Approval KEVIN SARGSYAN
Structural Steel Frame 3/12/2025 Partial Inspection KEVIN SARGSYAN
Deputy Other (see comments) 3/19/2025 Approved BOBBY KEY
Deputy Reinf. Concrete 3/19/2025 Approved BOBBY KEY
Structural Steel Frame 3/19/2025 Approved BOBBY KEY
Footing/Foundation/Slab 4/1/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval KEVIN SARGSYAN
Wood Frame 4/23/2025 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 9/17/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 9/19/2025 Approved KEVIN SARGSYAN
Green Building Rough 9/19/2025 Approved KEVIN SARGSYAN
Drywall Nailing 11/17/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 11/20/2025 Corrections Issued KEVIN SARGSYAN
Final 11/20/2025 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 11/20/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Approved KEVIN SARGSYAN
Final 12/1/2025 OK to Issue CofO KEVIN SARGSYAN