16110 W LEADWELL ST 91406

Certificate Information: 16110 W LEADWELL ST 91406

Application / Permit
24010-30000-02558
Plan Check / Job No.
B24WL01300
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-Story Detached ADU per Ordinance (LAMC 12.22 A.33 (c)-(d)) in the rear of the lot **3 of 3**
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
CofO Issued on 6/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 HOOMAN HAJIZADEH
Corrections Issued 7/9/2024 HOOMAN HAJIZADEH
Quality Review Completed 7/15/2024 CHIHARU SUZUKI
Building Plans Picked Up 7/15/2024 APPLICANT
Applicant returned to address corrections 8/2/2024 HOOMAN HAJIZADEH
Plan Check Approved 11/8/2024 HOOMAN HAJIZADEH
Issued 2/13/2025 APPLICANT
CofO in Progress 6/17/2026 MICHAEL CORTEZ
Permit Finaled 6/30/2026 RUBEN SALAS
CofO Issued 6/30/2026 RUBEN SALAS
Permit Finaled 6/30/2026 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/18/2024 SARAH YOUSSEF
Address approval Cleared 7/20/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/20/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/20/2024 CARLOS AGUILERA
Sewer availability Cleared 7/22/2024 CARLOS AGUILERA
Highway dedication Cleared 7/25/2024 CARLOS AGUILERA
Construction within easement Cleared 8/15/2024 OSCAR CASTRO
Permit Cleared 8/26/2024 CARLOS AGUILERA
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
Frnt yard landscape/Water mgmt Cleared 9/18/2024 YINGSHI HUANG
Hydrant and Access approval Cleared 10/23/2024 JOHN CONNEALLY

Contact Information

Architect Dehghan,, Hamid; Lic. No.: C35150 2355 WESTWOOD BLVD.   # 900    LOS ANGELES, CA 90064
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/10/2025 Corrections Issued CHRISTOPHER ROJAS
Pre-Inspection 4/10/2025 Partial Inspection CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/14/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Pre-Inspection 4/14/2025 Approved GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 4/25/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 4/25/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 4/29/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 4/29/2025 Partial Approval GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 4/30/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 4/30/2025 Partial Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 5/1/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/5/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 5/9/2025 Not Ready for Inspection SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 5/12/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 5/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 5/30/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 8/12/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 8/28/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 8/29/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 9/2/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 9/2/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 9/2/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 9/9/2025 Conditional Approval WAYNE REGESTER
BUILDING-Rough-Frame 9/10/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 9/10/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 9/16/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/17/2025 Approved GAREN HAYRAPETYAN
Insulation 9/24/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/24/2025 Not Ready for Inspection RYAN SALAZAR
Shower Pan 9/24/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/30/2025 Approved LOUIS ESCOTO
Shower Pan 9/30/2025 Approved LOUIS ESCOTO
Drywall Nailing 10/3/2025 Approved CHRISTOPHER MORFIN
Pre-Inspection 10/22/2025 Partial Inspection NICHOLAS TROWBRIDGE
Underground Mechanical 12/23/2025 Partial Approval MICHAEL CORTEZ
Sewer 2/3/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/14/2026 Corrections Issued JAVIER RAMOS JR
HVAC-Final 4/14/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/14/2026 Approved JAVIER RAMOS JR
Service/Power Release 4/14/2026 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 4/15/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 5/4/2026 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Final 5/5/2026 Approved KIRK SANDERS
Final 5/5/2026 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/5/2026 Approved KIRK SANDERS
Green Building Final 5/5/2026 Approved KIRK SANDERS
Service/Power Release 5/5/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 5/5/2026 Approved KIRK SANDERS
Service/Power Release 6/3/2026 Approved JOSE AVILA
Service/Power Release 6/4/2026 Approved JOSE AVILA
Final 6/12/2026 OK to Issue CofO MICHAEL CORTEZ