326-326 1/2 N OCCIDENTAL BLVD 90026

Certificate Information: 326-326 1/2 N OCCIDENTAL BLVD 90026

Application / Permit
24010-30000-02353
Plan Check / Job No.
B24WL01202
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story Duplex at front of the lot
Permit Issued
Issued on 5/21/2025
Issuing Office
Metro
Current Status
Issued on 5/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 REZA HAGHIGHAT
Corrections Issued 6/9/2024 REZA HAGHIGHAT
Quality Review Completed 6/10/2024 CHIHARU SUZUKI
Building Plans Picked Up 6/14/2024 APPLICANT
Plan Check Approved 3/4/2025 REZA HAGHIGHAT
No Progress 3/20/2025 REZA HAGHIGHAT
Plan Check Approved 3/30/2025 REZA HAGHIGHAT
Issued 5/21/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 6/11/2024 SARAH YOUSSEF
Highway dedication Cleared 6/13/2024 AMBER CAMPBELL
Frnt yard landscape/Water mgmt Cleared 6/24/2024 DANIEL CORONADO
Address approval Cleared 7/1/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 7/1/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/9/2024 TREVOR QUAN
Sewer availability Cleared 7/9/2024 TREVOR QUAN
Hydrant and Access approval Cleared 7/13/2024 JOHN CONNEALLY
Permit Cleared 7/25/2024 TREVOR QUAN
SB8 RUD Cleared 2/25/2025 LOUIE MILLER

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/26/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/26/2025 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 6/26/2025 Approved FREDDIE RIVERA
METHANE-Subgrade 6/26/2025 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/27/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 7/21/2025 Partial Approval FREDDIE RIVERA
Insulation 7/23/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Partial Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval FREDDIE RIVERA
Deputy Wood Construction 11/20/2025 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Approved ANTHONY RAMOS
ELECTRICAL-Rough 12/15/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 12/15/2025 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 12/16/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/17/2025 Approved FREDDIE RIVERA
Green Building Rough 12/17/2025 Approved FREDDIE RIVERA
MERV13>=Rough 12/17/2025 Approved FREDDIE RIVERA
METHANE-Rough 12/17/2025 Approved FREDDIE RIVERA
Insulation 12/22/2025 Corrections Issued ALEX COLIN
Drywall Nailing 1/9/2026 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/9/2026 Partial Approval FREDDIE RIVERA
Underground Mechanical 6/2/2026 Approved FREDDIE RIVERA