5212 N SATSUMA AVE 91601
Certificate Information: 5212 N SATSUMA AVE 91601
- Application / Permit
- 24010-30000-01987
- Plan Check / Job No.
- B24WL01015
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU per state law (CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)) *** 3 of 4 ***
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 5/30/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 5/30/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Plan Check Approved | 8/20/2024 | HOOMAN HAJIZADEH |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 7/28/2025 | JOSE AVILA |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2024 | EDGAR ALCARAZ |
| Highway dedication | Cleared | 6/1/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/3/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 6/4/2024 | SARAH YOUSSEF |
| Frnt yard landscape/Water mgmt | Cleared | 6/13/2024 | ASHLEY RODARTE |
| ZA Case | Cleared | 6/13/2024 | ASHLEY RODARTE |
| Hydrant and Access approval | Cleared | 7/9/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | EDGAR ALCARAZ |
| Construction near power lines | Cleared | 8/8/2024 | RIDWAN HARDY |
| SB8 RUD | Cleared | 8/8/2024 | ASHLEY MEDINA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 10/3/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/3/2024 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 10/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 10/28/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 11/12/2024 | Conditional Approval | ROBERT GOLD |
| Drywall Nailing | 11/13/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 12/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/13/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/24/2024 | Partial Approval | JOSE AVILA |
| Special/Order Compliance | 12/24/2024 | Approved | JOSE AVILA |
| Shower Pan | 12/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 1/9/2025 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 1/10/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/16/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/17/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/17/2025 | Conditional Approval | JOSE AVILA |
| Green Building Rough | 1/17/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/17/2025 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 1/17/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/5/2025 | Approved | JOSE AVILA |
| Insulation | 2/10/2025 | Approved | JOSE AVILA |
| Special/Order Compliance | 2/10/2025 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 2/19/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/2/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/3/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | JOSE AVILA |
| Green Building Final | 7/7/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Required | JOSE AVILA |
| Smoke Detectors | 7/7/2025 | Approved | JOSE AVILA |
| Final | 7/24/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/24/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/25/2025 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 7/25/2025 | Approved | JOSE AVILA |