2002-2002 1/2 S HILLCREST DR 90016
Certificate Information: 2002-2002 1/2 S HILLCREST DR 90016
- Application / Permit
- 24010-30000-01891
- Plan Check / Job No.
- B24WL00949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story 2 ADUs at rear of the lot per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/12/2024
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2024 | REZA HAGHIGHAT |
| Corrections Issued | 5/13/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 5/14/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 5/21/2024 | APPLICANT |
| Plan Check Approved | 8/7/2024 | REZA HAGHIGHAT |
| Issued | 8/12/2024 | APPLICANT |
| CofO in Progress | 9/23/2025 | JUSTIN HAWLEY |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
| CofO Issued | 9/26/2025 | DEROLD HAUFF |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/12/2024 | MARTIN FRAGOSO |
| Address approval | Cleared | 5/17/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/17/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 6/8/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 6/25/2024 | KURT CORRAL |
| Construction near power lines | Cleared | 7/25/2024 | RIDWAN HARDY |
| SB8 RUD | Cleared | 8/1/2024 | DORIS KWOK |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/5/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 9/19/2024 | Corrections Issued | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Approved | WILLIAM SIERRA |
| Pre-Inspection | 9/20/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 11/21/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 11/21/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 11/21/2024 | Approved | JUSTIN HAWLEY |
| Sewer | 11/27/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 11/27/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | JUSTIN HAWLEY |
| HVAC-Rough | 12/18/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Deputy Wood Construction | 12/19/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/3/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 1/3/2025 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 1/3/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 1/16/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/16/2025 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 1/24/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 1/24/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/24/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/5/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 3/20/2025 | Corrections Issued | JOSH MEISTER |
| Underground Mechanical | 3/24/2025 | Partial Approval | JOSH MEISTER |
| ELECTRICAL-Final | 6/17/2025 | No Access for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 6/17/2025 | No Access for Inspection | JUSTIN HAWLEY |
| Final | 8/12/2025 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Final | 9/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 9/17/2025 | Approved | JUSTIN HAWLEY |
| Green Building Final | 9/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Service/Power Release | 9/17/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 9/17/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/23/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 9/23/2025 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 9/23/2025 | Approved | JUSTIN HAWLEY |