2002-2002 1/2 S HILLCREST DR 90016

Certificate Information: 2002-2002 1/2 S HILLCREST DR 90016

Application / Permit
24010-30000-01891
Plan Check / Job No.
B24WL00949
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story 2 ADUs at rear of the lot per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 8/12/2024
Issuing Office
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/8/2024 REZA HAGHIGHAT
Corrections Issued 5/13/2024 REZA HAGHIGHAT
Quality Review Completed 5/14/2024 KAVIAN REFAHI
Building Plans Picked Up 5/21/2024 APPLICANT
Plan Check Approved 8/7/2024 REZA HAGHIGHAT
Issued 8/12/2024 APPLICANT
CofO in Progress 9/23/2025 JUSTIN HAWLEY
Permit Finaled 9/26/2025 DEROLD HAUFF
CofO Issued 9/26/2025 DEROLD HAUFF
Permit Finaled 9/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 5/12/2024 MARTIN FRAGOSO
Address approval Cleared 5/17/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 5/17/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/8/2024 JESSICA OPINION
Sewer availability Cleared 6/8/2024 JESSICA OPINION
Hydrant and Access approval Cleared 6/25/2024 KURT CORRAL
Construction near power lines Cleared 7/25/2024 RIDWAN HARDY
SB8 RUD Cleared 8/1/2024 DORIS KWOK

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/5/2024 Partial Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/19/2024 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 9/19/2024 Corrections Issued WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 9/20/2024 Approved WILLIAM SIERRA
Pre-Inspection 9/20/2024 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval JUSTIN HAWLEY
ELECTRICAL-Rough 11/21/2024 Approved JUSTIN HAWLEY
HVAC-Rough 11/21/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 11/21/2024 Approved JUSTIN HAWLEY
Sewer 11/27/2024 Approved JUSTIN HAWLEY
Underground Mechanical 11/27/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval JUSTIN HAWLEY
HVAC-Rough 12/18/2024 Not Ready for Inspection JUSTIN HAWLEY
Deputy Wood Construction 12/19/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 1/3/2025 Approved JUSTIN HAWLEY
Green Building Rough 1/3/2025 Approved JUSTIN HAWLEY
HVAC-Rough 1/3/2025 Approved JUSTIN HAWLEY
Verify Sprinkler Sign Off 1/3/2025 Approved JUSTIN HAWLEY
Insulation 1/16/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/16/2025 Partial Approval JUSTIN HAWLEY
Drywall Nailing 1/24/2025 Approved JUSTIN HAWLEY
Insulation 1/24/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/24/2025 Approved JUSTIN HAWLEY
Shower Pan 2/5/2025 Approved JUSTIN HAWLEY
Underground Mechanical 3/20/2025 Corrections Issued JOSH MEISTER
Underground Mechanical 3/24/2025 Partial Approval JOSH MEISTER
ELECTRICAL-Final 6/17/2025 No Access for Inspection JUSTIN HAWLEY
HVAC-Final 6/17/2025 No Access for Inspection JUSTIN HAWLEY
Final 8/12/2025 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Not Ready JUSTIN HAWLEY
Final 9/17/2025 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 9/17/2025 Approved JUSTIN HAWLEY
Green Building Final 9/17/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Not Required JUSTIN HAWLEY
Service/Power Release 9/17/2025 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 9/17/2025 Approved JUSTIN HAWLEY
Final 9/23/2025 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 9/23/2025 Approved JUSTIN HAWLEY
Service/Power Release 9/23/2025 Approved JUSTIN HAWLEY