6054 W 82ND ST 90045

Certificate Information: 6054 W 82ND ST 90045

Application / Permit
24010-30000-01776
Plan Check / Job No.
B24WL00901
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 2-story ADU per Ordinance (LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 9/6/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/1/2024 HOOMAN HAJIZADEH
Corrections Issued 5/14/2024 HOOMAN HAJIZADEH
Quality Review Completed 5/24/2024 KAVIAN REFAHI
Building Plans Picked Up 5/31/2024 APPLICANT
Applicant returned to address corrections 8/16/2024 HOOMAN HAJIZADEH
Plan Check Approved 9/3/2024 HOOMAN HAJIZADEH
Issued 9/6/2024 APPLICANT
CofO in Progress 8/27/2025 JESUS PINEDA
Permit Finaled 8/27/2025 RICHARD STEINBACH
CofO Issued 8/27/2025 RICHARD STEINBACH
Permit Finaled 8/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/25/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 6/25/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 6/25/2024 DIANA RENTERIA
Sewer availability Cleared 7/1/2024 DIANA RENTERIA
Construction near power lines Cleared 7/8/2024 ENRIQUE ACOSTA
Low Impact Development (LID) Cleared 7/9/2024 MARCO SANCHEZ
Specific Plan Cleared 7/23/2024 FREDDY GARCIA

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 2632 WILSHIRE BLVD #363      SANTA MONICA, CA 90403
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/16/2024 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 11/8/2024 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 11/8/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 1/29/2025 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 1/29/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 1/29/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/7/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 2/7/2025 Approved TEMISTOCLES CAAL
Green Building Rough 2/7/2025 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 2/7/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 2/10/2025 Approved TEMISTOCLES CAAL
Insulation 2/18/2025 Approved EVAN COOPER
Drywall Nailing 2/21/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/3/2025 Not Ready for Inspection JESUS PINEDA
Shower Pan 4/3/2025 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 4/4/2025 Approved JESUS PINEDA
Shower Pan 4/4/2025 Approved JESUS PINEDA
Underground Mechanical 4/4/2025 Approved JESUS PINEDA
ELECTRICAL-Final 7/24/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 7/25/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Final 7/29/2025 Approved JESUS PINEDA
HVAC-Final 7/29/2025 Approved JESUS PINEDA
Final 8/1/2025 Corrections Issued JESUS PINEDA
Green Building Final 8/1/2025 Approved JESUS PINEDA
PLUMBING-Final 8/1/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Required JESUS PINEDA
Service/Power Release 8/1/2025 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 8/1/2025 Approved JESUS PINEDA
Special/Order Compliance 8/18/2025 Partial Inspection JESUS PINEDA
Final 8/26/2025 OK to Issue CofO JESUS PINEDA
Service/Power Release 8/26/2025 Approved JESUS PINEDA