1321 1/2 S KENISTON AVE 90019
Certificate Information: 1321 1/2 S KENISTON AVE 90019
- Application / Permit
- 24010-30000-01379
- Plan Check / Job No.
- B24WL00723
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU WITH ATTACHED ONE CAR GARAGE. PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 2/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2024 | ALFREDO JARA |
| Corrections Issued | 4/7/2024 | ALFREDO JARA |
| Building Plans Picked Up | 5/24/2024 | APPLICANT |
| Plan Check Approved | 2/3/2025 | ALFREDO JARA |
| Issued | 2/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/28/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 5/28/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 5/28/2024 | JUSTIN BICOL |
| ZI | Cleared | 6/21/2024 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 9/23/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/23/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 6/6/2025 | Partial Approval | JUSTIN HAWLEY |
| METHANE-Rough | 6/6/2025 | Partial Approval | JUSTIN HAWLEY |
| METHANE-Subgrade | 6/6/2025 | Partial Approval | JUSTIN HAWLEY |
| Pre-Inspection | 6/6/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 6/6/2025 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Corrections Issued | JUSTIN HAWLEY |
| Special/Order Compliance | 6/24/2025 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 6/25/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 6/25/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 6/25/2025 | Approved | ARTHUR NEGRETE |
| Deputy Reinf. Concrete | 6/26/2025 | Conditional Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Partial Approval | JUSTIN HAWLEY |
| Deputy Wood Construction | 7/16/2025 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Wood Construction | 7/18/2025 | Conditional Approval | RONNIE MEDINA |
| Special/Order Compliance | 10/21/2025 | Partial Inspection | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Approved | JUSTIN HAWLEY |
| Sewer | 3/26/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 3/31/2026 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/31/2026 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 4/14/2026 | Approved | JUSTIN HAWLEY |
| Sewer | 4/14/2026 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 4/14/2026 | Partial Approval | JUSTIN HAWLEY |