4502 N LOWELL AVE 90032
Certificate Information: 4502 N LOWELL AVE 90032
- Application / Permit
- 24010-30000-01321
- Plan Check / Job No.
- B24WL00680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story S.F.D. with attached garage
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 4/11/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 4/16/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/18/2024 | APPLICANT |
| Plan Check Approved | 5/24/2024 | HOOMAN HAJIZADEH |
| Issued | 7/2/2024 | APPLICANT |
| CofO in Progress | 5/16/2025 | LILIANA PORTILLO |
| Permit Finaled | 5/17/2025 | DEROLD HAUFF |
| CofO Issued | 5/17/2025 | DEROLD HAUFF |
| Permit Finaled | 5/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/17/2024 | SAMUEL LINN |
| Address approval | Cleared | 4/19/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 4/25/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 4/26/2024 | DAVID VO |
| Hydrant and Access approval | Cleared | 5/11/2024 | KURT CORRAL |
| GPI Written Notices | Cleared | 5/24/2024 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 5/24/2024 | HOOMAN HAJIZADEH |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Barajas,, Jorge; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/9/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 8/9/2024 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 8/9/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/15/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Corrections Issued | BRENDAN MORELLI |
| Wood Frame | 9/5/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 11/19/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/19/2024 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 11/21/2024 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | WILLIAM SIERRA |
| Insulation | 12/4/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/4/2024 | Partial Approval | LILIANA PORTILLO |
| Shower Pan | 12/4/2024 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 12/12/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 12/12/2024 | Approved | LUIS CASTRO |
| Shower Pan | 12/12/2024 | Corrections Issued | LUIS CASTRO |
| Shower Pan | 12/17/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/27/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/23/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/23/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/2/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/5/2025 | Approved | LILIANA PORTILLO |
| Final | 5/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 5/5/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 5/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/15/2025 | OK to Issue CofO | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 5/15/2025 | Approved | LILIANA PORTILLO |