1210 N ORANGE DR 90038

Certificate Information: 1210 N ORANGE DR 90038

Application / Permit
24010-30000-00915
Plan Check / Job No.
B24WL00504
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story S.FD. w/ attached 2-car garage in middle of the lot
Permit Issued
Issued on 2/4/2025
Issuing Office
Metro
Current Status
Issued on 2/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/5/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 REZA HAGHIGHAT
Corrections Issued 3/9/2024 REZA HAGHIGHAT
Quality Review Completed 3/21/2024 KAVIAN REFAHI
Building Plans Picked Up 3/28/2024 APPLICANT
Plan Check Approved 10/28/2024 REZA HAGHIGHAT
Issued 2/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/11/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/12/2024 JEANIE LAM
Sewer availability Cleared 3/12/2024 JEANIE LAM
ZA Case Cleared 3/27/2024 SPENCER WEJROWSKI
Frnt yard landscape/Water mgmt Cleared 4/2/2024 SPENCER WEJROWSKI
Hydrant and Access approval Cleared 4/12/2024 JOHN CONNEALLY
SB8 RUD Cleared 5/13/2024 KEVIN SCHULTZ
Highway dedication Cleared 6/10/2024 AMBER CAMPBELL
Low Impact Development Cleared 6/25/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/28/2024 AMBER CAMPBELL

Contact Information

Contractor Greencollar Construction Inc; Lic. No.: 957375-B 575 ELM AVE APT 9      LONG BEACH, CA 90802

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/27/2025 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/7/2025 Approved CRAIG VAUGHAN
Deputy Steel/Welding 3/19/2025 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/3/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/3/2025 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/3/2025 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/9/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/9/2025 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/9/2025 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 5/6/2025 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 5/15/2025 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 5/15/2025 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 5/15/2025 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/15/2025 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 6/25/2025 Corrections Issued BRENDAN MORELLI
HVAC-Rough 6/25/2025 Approved BRENDAN MORELLI
ELECTRICAL-Rough 6/26/2025 Approved BRIAN SULLIVAN
Green Building Rough 6/26/2025 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/26/2025 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 7/9/2025 Conditional Approval BRIAN SULLIVAN
Green Building Rough 7/9/2025 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/9/2025 Approved BRIAN SULLIVAN
PLUMBING-Rough 7/15/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/17/2025 Partial Approval CRAIG VAUGHAN
Insulation 7/22/2025 Corrections Issued BRENDAN MORELLI
Drywall Nailing 8/14/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 8/14/2025 Approved ROY SPAULDING
Sewer 12/23/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/9/2026 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 4/24/2026 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 5/4/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 5/4/2026 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 5/12/2026 Corrections Issued CRAIG VAUGHAN