1237 N ORANGE DR 90038
Certificate Information: 1237 N ORANGE DR 90038
- Application / Permit
- 24010-30000-00859
- Plan Check / Job No.
- B24WL00477
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 3-story SFD at front of the lot ** 1 of 3 **
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 3/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | KAVIAN REFAHI |
| Corrections Issued | 3/16/2024 | KAVIAN REFAHI |
| Quality Review Completed | 3/20/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 3/26/2024 | APPLICANT |
| Plan Check Approved | 7/17/2024 | KAVIAN REFAHI |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 3/27/2026 | CRAIG VAUGHAN |
| CofO Issued | 3/28/2026 | DEROLD HAUFF |
| Permit Finaled | 3/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 3/15/2024 | ALYSSA FLORES |
| Address approval | Cleared | 3/20/2024 | KHAING AYE |
| Frnt yard landscape/Water mgmt | Cleared | 4/9/2024 | FIPE LEILUA |
| Low Impact Development (LID) | Cleared | 4/9/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 4/11/2024 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 4/12/2024 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 5/10/2024 | JESSICA OPINION |
| Highway dedication | Cleared | 6/26/2024 | TREVOR QUAN |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD+ 900 LOS ANGELES, CA 90064 |
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/8/2024 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/11/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 10/15/2024 | Approved | RAUL BARAJAS |
| Sewer | 10/28/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 2/25/2025 | Partial Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/5/2025 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 3/5/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 3/7/2025 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/10/2025 | No Access for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/12/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/19/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 3/19/2025 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/16/2025 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/16/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/28/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 4/28/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 4/29/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/5/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 5/20/2025 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 5/29/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/9/2025 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 9/29/2025 | Partial Approval | CRAIG VAUGHAN |
| Final | 1/30/2026 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Required | CRAIG VAUGHAN |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 1/30/2026 | Approved | CRAIG VAUGHAN |
| Final | 3/10/2026 | Partial Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/10/2026 | Approved | CRAIG VAUGHAN |
| Final | 3/16/2026 | Partial Inspection | CRAIG VAUGHAN |
| Final | 3/17/2026 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/17/2026 | Approved | CRAIG VAUGHAN |
| Green Building Final | 3/17/2026 | Approved | CRAIG VAUGHAN |
| Final | 3/26/2026 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 3/26/2026 | Approved | CRAIG VAUGHAN |