1237 N ORANGE DR 90038

Certificate Information: 1237 N ORANGE DR 90038

Application / Permit
24010-30000-00859
Plan Check / Job No.
B24WL00477
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 3-story SFD at front of the lot ** 1 of 3 **
Permit Issued
Issued on 9/5/2024
Issuing Office
Current Status
CofO Issued on 3/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2024 APPLICANT
Assigned to Plan Check Engineer 3/13/2024 KAVIAN REFAHI
Corrections Issued 3/16/2024 KAVIAN REFAHI
Quality Review Completed 3/20/2024 REZA HAGHIGHAT
Building Plans Picked Up 3/26/2024 APPLICANT
Plan Check Approved 7/17/2024 KAVIAN REFAHI
Issued 9/5/2024 APPLICANT
CofO in Progress 3/27/2026 CRAIG VAUGHAN
CofO Issued 3/28/2026 DEROLD HAUFF
Permit Finaled 3/28/2026 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 3/15/2024 ALYSSA FLORES
Address approval Cleared 3/20/2024 KHAING AYE
Frnt yard landscape/Water mgmt Cleared 4/9/2024 FIPE LEILUA
Low Impact Development (LID) Cleared 4/9/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/11/2024 ERIK BEASLEY
Hydrant and Access approval Cleared 4/12/2024 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 5/10/2024 JESSICA OPINION
Sewer availability Cleared 5/10/2024 JESSICA OPINION
Highway dedication Cleared 6/26/2024 TREVOR QUAN

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD BLVD+   900    LOS ANGELES, CA 90064
Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/26/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/8/2024 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/10/2024 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/11/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 10/11/2024 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/15/2024 Approved CRAIG VAUGHAN
Pre-Inspection 10/15/2024 Approved RAUL BARAJAS
Sewer 10/28/2024 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 2/25/2025 Partial Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/5/2025 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 3/7/2025 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/10/2025 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/12/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/19/2025 Approved CRAIG VAUGHAN
HVAC-Rough 3/19/2025 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/16/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/16/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/28/2025 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 4/28/2025 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/28/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/29/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/29/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/5/2025 Approved CRAIG VAUGHAN
Insulation 5/20/2025 Corrections Issued BRENDAN MORELLI
Insulation 5/29/2025 Approved CRAIG VAUGHAN
Drywall Nailing 6/9/2025 Approved CRAIG VAUGHAN
Underground Mechanical 9/29/2025 Partial Approval CRAIG VAUGHAN
Final 1/30/2026 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Required CRAIG VAUGHAN
Service/Power Release 1/30/2026 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 1/30/2026 Approved CRAIG VAUGHAN
Final 3/10/2026 Partial Inspection CRAIG VAUGHAN
Service/Power Release 3/10/2026 Approved CRAIG VAUGHAN
Final 3/16/2026 Partial Inspection CRAIG VAUGHAN
Final 3/17/2026 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 3/17/2026 Approved CRAIG VAUGHAN
Green Building Final 3/17/2026 Approved CRAIG VAUGHAN
Final 3/26/2026 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 3/26/2026 Approved CRAIG VAUGHAN