5315-5317 N BEN AVE 91607

Certificate Information: 5315-5317 N BEN AVE 91607

Application / Permit
24010-30000-00827
Plan Check / Job No.
B24WL00462
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
3 STORY DUPLEX WITH ATTACH GARAGE (front bldg) ---1 OF 2---
Permit Issued
Issued on 3/11/2025
Issuing Office
Current Status
CofO Issued on 6/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 KAVIAN REFAHI
Corrections Issued 3/9/2024 KAVIAN REFAHI
Quality Review Completed 3/13/2024 REZA HAGHIGHAT
Building Plans Picked Up 3/13/2024 APPLICANT
Disabled Access Plans Picked Up 4/4/2024 APPLICANT
Applicant returned to address corrections 12/16/2024 KAVIAN REFAHI
Plan Check Approved 12/27/2024 KAVIAN REFAHI
Issued 3/11/2025 APPLICANT
CofO in Progress 5/21/2026 JAVIER RAMOS JR
CofO Issued 6/10/2026 RUBEN SALAS
Permit Finaled 6/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/9/2024 LEE GUILBEAUX
Highway dedication Cleared 3/9/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/9/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/11/2024 LEE GUILBEAUX
Sewer availability Cleared 3/11/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/12/2024 JOHN CONNEALLY
SB8 RUD Cleared 4/15/2024 SHARON WILLIAMS
Low Impact Development (LID) Cleared 4/24/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/24/2024 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 12/10/2024 MATHEW QUAN
Opn space landscape/Water mgmt Cleared 12/10/2024 MATHEW QUAN
Specific Plan Cleared 12/10/2024 MATHEW QUAN
ZI Cleared 12/10/2024 MATHEW QUAN
Building over 36-ft Cleared 12/16/2024 CALOSHA APPROVED

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Onward Builders Llc; Lic. No.: 1084275-B 750 N SAN VICENTE BLVD STE 800      WEST HOLLYWOOD, CA 90069
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2025 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 4/3/2025 Corrections Issued JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/14/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/14/2025 Corrections Issued JAVIER RAMOS JR
Deputy Steel/Welding 5/1/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/2/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 5/2/2025 Approved JAVIER RAMOS JR
Deputy Wood Construction 5/8/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 6/9/2025 Conditional Approval RAUL OLAGI
Deputy Wood Construction 6/24/2025 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 7/11/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/4/2025 Corrections Issued JOSE AVILA
HVAC-Rough 8/4/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 8/12/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 8/12/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Corrections Issued JAVIER RAMOS JR
Green Building Rough 8/12/2025 Approved JAVIER RAMOS JR
HVAC-Rough 8/12/2025 Not Ready for Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 8/12/2025 Approved JAVIER RAMOS JR
HVAC-Rough 8/28/2025 Approved JAVIER RAMOS JR
Insulation 9/8/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 9/8/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 9/11/2025 Not Ready for Inspection JAVIER RAMOS JR
Insulation 9/11/2025 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 9/11/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 9/15/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Approved JAVIER RAMOS JR
Insulation 9/15/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 9/15/2025 Partial Approval JAVIER RAMOS JR
Drywall Nailing 9/22/2025 Corrections Issued JAVIER RAMOS JR
Shower Pan 9/22/2025 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 9/24/2025 Approved JAVIER RAMOS JR
Insulation 9/24/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/24/2025 Approved JAVIER RAMOS JR
Shower Pan 9/24/2025 Approved JAVIER RAMOS JR
Special/Order Compliance 11/19/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 5/8/2026 Approved JAVIER RAMOS JR
Final 5/8/2026 No Access for Inspection JAVIER RAMOS JR
Green Building Final 5/8/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 5/8/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/8/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 5/8/2026 Approved JAVIER RAMOS JR
Smoke Detectors 5/8/2026 Approved JAVIER RAMOS JR
Final 5/20/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/20/2026 Approved JAVIER RAMOS JR