817 N VINE ST 90038
Certificate Information: 817 N VINE ST 90038
- Application / Permit
- 24010-30000-00712
- Plan Check / Job No.
- B24LA01231
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Patio Cover
- Work Description
- eplan ** Construction of a shade sail structures over existing outdoor area. ** 2 of 2 **
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | KAVIAN REFAHI |
| Assigned to Zoning Architect | 2/15/2024 | KAVIAN REFAHI |
| Corrections Issued | 2/20/2024 | KAVIAN REFAHI |
| Quality Review Completed | 3/5/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/28/2024 | KAVIAN REFAHI |
| Plan Check Approved | 6/3/2024 | KAVIAN REFAHI |
| Issued | 7/29/2024 | APPLICANT |
| CofO in Progress | 4/7/2025 | RAFAEL CORTES |
| Permit Finaled | 4/7/2025 | RAFAEL ESPINOZA |
| CofO Issued | 4/7/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 4/7/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| HPOZ | Cleared | 4/3/2024 | LAMBERT GIESSINGER |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2024 | DAVID LOPEZ |
| ZI | Cleared | 4/9/2024 | DALIA MOKAYED |
| Low Impact Development (LID) | Cleared | 4/14/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/17/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 5/17/2024 | GILBERT URREA |
| "Q" conditions | Cleared | 5/22/2024 | DALIA MOKAYED |
| DAS Clearance | Cleared | 5/30/2024 | KAVIAN REFAHI |
Contact Information
| Contractor | Holwick Constructors Inc; Lic. No.: 766151-B | 200 N WESTLAKE BLVD SUITE 102 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/10/2024 | Corrections Issued | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 9/23/2024 | Approved | RAFAEL CORTES |
| Final | 10/17/2024 | Conditional Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/17/2024 | Approved | RAFAEL CORTES |
| Green Building Final | 10/17/2024 | Approved | RAFAEL CORTES |
| Green Building Rough | 10/17/2024 | Approved | RAFAEL CORTES |
| METHANE-Barrier | 10/17/2024 | Approved | RAFAEL CORTES |
| METHANE-Final | 10/17/2024 | Approved | RAFAEL CORTES |
| METHANE-Rough | 10/17/2024 | Approved | RAFAEL CORTES |
| METHANE-Subgrade | 10/17/2024 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 10/17/2024 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 10/17/2024 | Approved | RAFAEL CORTES |
| Wood Frame | 10/17/2024 | Approved | RAFAEL CORTES |
| Final | 4/7/2025 | OK to Issue CofO | RAFAEL CORTES |