11914 W EXPOSITION BLVD 90064
Certificate Information: 11914 W EXPOSITION BLVD 90064
- Application / Permit
- 24010-30000-00307
- Plan Check / Job No.
- B24WL00209
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- New 2-story detached 2-car garage with rec-room above at rear of the lot
- Permit Issued
- Issued on 11/20/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | YASHAR EMAMI |
| Corrections Issued | 2/20/2024 | YASHAR EMAMI |
| Quality Review Completed | 2/27/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 3/1/2024 | APPLICANT |
| Applicant returned to address corrections | 9/18/2024 | YASHAR EMAMI |
| Plan Check Approved | 11/20/2024 | YASHAR EMAMI |
| Issued | 11/20/2024 | APPLICANT |
| CofO in Progress | 4/2/2026 | WILBER ROSALES |
| Permit Finaled | 4/21/2026 | RICHARD STEINBACH |
| CofO Issued | 4/21/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | DARIN LAM |
| Sewer availability | Cleared | 4/30/2024 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 6/13/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/18/2024 | ANDREA SAINT-ANTONIN |
| Metro Rail approval | Cleared | 6/28/2024 | JENNIFER SU |
| Specific Plan | Cleared | 8/19/2024 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/7/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 3/10/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 3/28/2025 | Partial Approval | KIRK SANDERS |
| Deputy Steel/Welding | 4/23/2025 | Conditional Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 5/7/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 5/7/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/8/2025 | Approved | KIRK SANDERS |
| Deputy Steel/Welding | 5/19/2025 | Conditional Approval | KIRK SANDERS |
| Structural Steel Frame | 5/20/2025 | Conditional Approval | KIRK SANDERS |
| Underground Mechanical | 5/20/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 6/3/2025 | Corrections Issued | KIRK SANDERS |
| Structural Steel Frame | 6/3/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 8/6/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/7/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | EVAN COOPER |
| Green Building Rough | 9/2/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 9/2/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/12/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/12/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 9/19/2025 | Approved | ARAM AVEDISIAN |
| Sewer | 10/24/2025 | Approved | KENNETH NAGLE |
| Drywall Nailing | 10/31/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 2/4/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 2/4/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/18/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 2/25/2026 | Conditional Approval | MICHAEL ALLEN |
| Final | 4/1/2026 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 4/1/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 4/1/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 4/1/2026 | Approved | WILBER ROSALES |
| Smoke Detectors | 4/1/2026 | Approved | WILBER ROSALES |