7720 N CLEON AVE 91352
Certificate Information: 7720 N CLEON AVE 91352
- Application / Permit
- 24010-20002-00922
- Plan Check / Job No.
- B25VN01969
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO 24010-20001-00922. TO REVISE THE SETBACKS ON THE REAR AND ADD THE 16'-0" X 12'-9" ATTACHED STORAGE.
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 1/27/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/30/2025 | GIOVANNY CHAVEZ |
| Issued | 1/30/2025 | APPLICANT |
| Permit Finaled | 1/2/2026 | MATTHEW NELSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 1/29/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/29/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 2/25/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/6/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 3/6/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/21/2025 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/21/2025 | No Access for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | No Access for Inspection | MATTHEW NELSON |
| Green Building Rough | 3/21/2025 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/24/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/24/2025 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/18/2025 | Partial Approval | DAVID ANDERSON |
| HVAC-Final | 4/23/2025 | Corrections Issued | DAVID MATSON |
| Insulation | 4/24/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 1/2/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/2/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/2/2026 | Approved | MATTHEW NELSON |
| Final | 1/2/2026 | Permit Finaled | MATTHEW NELSON |
| Green Building Final | 1/2/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/2/2026 | Approved | MATTHEW NELSON |
| Grounding or Bonding | 1/2/2026 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/2/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 1/2/2026 | Approved | MATTHEW NELSON |
| Service/Power Release | 1/2/2026 | Approved | MATTHEW NELSON |
| Smoke Detectors | 1/2/2026 | Approved | MATTHEW NELSON |