13190 W CORCORAN ST 91340
Certificate Information: 13190 W CORCORAN ST 91340
- Application / Permit
- 24010-20000-05390
- Plan Check / Job No.
- B24VN27243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN- (N) DETACHED ACCESSORY DWELLING UNIT PER PER LAMC 12.22 A.33(c) AND (d) . ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/8/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 1/16/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 1/31/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 4/8/2025 | APPLICANT |
| CofO in Progress | 3/19/2026 | MICHEL ABAJAN |
| CofO Issued | 4/16/2026 | RUBEN SALAS |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | RYAN CASTRO |
| ZI | Cleared | 1/9/2025 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/10/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 1/29/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Berg Development Inc; Lic. No.: 1111136-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/8/2025 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/12/2025 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/19/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/4/2025 | Partial Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 7/18/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 7/25/2025 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/25/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/25/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | MICHEL ABAJAN |
| Insulation | 8/11/2025 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 9/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 9/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 9/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 9/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 10/14/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/16/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 3/10/2026 | Approved | MICHEL ABAJAN |
| Final | 3/10/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 3/10/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/10/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 3/10/2026 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 3/10/2026 | Approved | MICHEL ABAJAN |
| Final | 3/18/2026 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | MICHEL ABAJAN |